The Prospector News

Champion Iron Announces an After-Tax IRR of 33.4% in Feasibility Study for the Phase II Expansion at Bloom Lake

You have opened a direct link to the current edition PDF

Open PDF Close
Uncategorized

Share this news article

Champion Iron Announces an After-Tax IRR of 33.4% in Feasibility Study for the Phase II Expansion at Bloom Lake

 

 

 

 

 

Champion Iron Limited (TSX: CIA) (ASX: CIA) is pleased to announce positive results of the Phase II Feasibility Study prepared pursuant to National Instrument 43-101 – Standards of Disclosure for Mineral Projects for the Bloom Lake Mining Complex located near the town of Fermont, in north-eastern Quebec. The Feasibility Study envisions further exploiting Bloom Lake which would increase overall capacity from 7.4Mtpa to 15Mtpa of 66.2% Fe iron ore concentrate.

 

All amounts stated in this news release are in Canadian dollars unless otherwise indicated.

 

  1. FEASIBILITY STUDY HIGHLIGHTS PHASE II

 

 

Base case assuming long-term price of US$68.2/t P62 and US$83.9/t P65 iron ore price CFR China
  CA$ US$
NPV – Pre-tax NPV8% of $1,532 million 
– After-tax NPV8% of $956 million 
– Pre-tax NPV8% of $3,762 million combining Phase I & II
– After-tax NPV8% of $2,384 million combining Phase I & II
– Pre-tax NPV8% of $1,160 million 
– After-tax NPV8% of $724 million 
– Pre-tax NPV8% of $2,850 million combining Phase I & II
– After-tax NPV8% of $1,806 million combining Phase I & II
IRR Pre-tax IRR of 42.4% or after-tax IRR of 33.4% with a 2.4 years payback on initial capital
Iron ore price Based on $110.7/t P65 iron ore price CFR China Based on $83.9/t P65 iron ore price CFR China
Initial CAPEX $589.8 million $446.8 million
Total cash cost1 $46.6/t FOB Sept-Îles $35.4/t FOB Sept-Îles
Sustaining capital $4.4$/t over the LoM $3.3$/t over the LoM
All-in sustaining cost1 $52.3/t FOB Sept-Îles $39.7/t FOB Sept-Îles
Production Estimated average annual production of 15 million tonnes of 66.2% Fe iron ore
Construction period 21 months
Mine life Current study mine life of 20 years
Mineral reserves Bloom Lake reserves estimated at 807 million tonnes at an average grade of 29.0% Fe
Recovery Average metallurgical recovery of 82.4% relative to average plant feed grade of 29.0% Fe

 

____________________________
Cash cost and all-in sustaining costs are non-IFRS financial performance measures with no standard definition under IFRS. The Company provides them as supplementary information that management believes may be useful to investors to explain the Company’s financial results.

 

 

Champion Iron CEO, Mr David Cataford, said, “This is a positive outcome for the Company as Phase II would further position Champion as one of the largest high-grade iron ore producers in the world. Based on conservative assumptions compared to current spot price, the Phase II Feasibility Study demonstrates that this expansion at Bloom Lake may drive additional value to shareholders and allow the Company to continue on its recent growth trajectory. In fact, we believe that very few iron ore projects offer the potential of 20+ years of production at industry-low operating costs, whilst being strategically located in close proximity to all necessary infrastructure and situated in what we consider to be a superior mining jurisdiction. Consistent with our commitment to offer accretive growth while managing dilution, we are approaching the project diligently by advancing key long-lead time items and will look at optimal sources of capital to further advance the project in due time.”

 

The Feasibility Study conducted by BBA Inc. evaluated the life-of-mine (“LoM”) option for expanded mining and processing to maximize the value of the mineral resource at Bloom Lake. The Feasibility Study evaluates the combined Phase I and II mining plan, current concentrator plant at Phase I and completion of the Phase II concentrator plant. Results of the Study recommend an expansion of Bloom Lake, resulting in a LoM production averaging 15 Mtpa of 66.2% Fe iron ore concentrate. Based on the new optimized mine plan, the mining rate at Bloom Lake would also be increased to accelerate the supply of ore to the expanded facilities, while maintaining a LoM of 20 years. Pursuant to the strong economics outlined in the Feasibility Study, the Company’s board of directors has approved an initial budget of $68 million to advance the project during the remainder of 2019, which is expected to meet the timetable detailed in the Feasibility Study. The approved budget will be funded from cash on hand and existing debt facilities. Finalization of additional funding sources for the project is expected to be completed before mid-2020. 

 

The processing plant for the Phase II concentrator is based on the currently operating Phase I design with minor changes to further improve performance. The recovery circuit is very similar to the Phase I concentrator with the addition of a stage of scavenger up current classifier to increase recovery and improve response to feed variations.

 

Most of the major equipment, with the exception of the gravity circuit equipment that was used as part of the Phase I restart project, was sourced on-site from the previous owner’s Phase II expansion project which was interrupted in 2012.

 

The base case economic assumption utilizes a conservative blended average gross realized price at 66.2% Fe CFR China of US$84.1/t for the LoM. The P65 analyst consensus was utilized for years 1 to 3. For the remaining LoM, the iron price at 66.2% is based on the average of the P65 analyst long-term consensus and the P62 3-year trailing average with a 15% premium. These price assumptions compare with a spot price at P65 of US$124.7/t as of June 13, 2019, of which Bloom Lake’s 66.2% Fe material receives a premium.

 

  1. ECONOMIC SUMMARY

 

The economic sensitivity analysis uses the P65 pricing which compares to a spot price of US$124.7 (as at June 13, 2019).

 

  CA$ US$ CA$ US$ CA$ US$
Iron ore based on P65 $US/t CFR China 105.2/t 79.7/t 111.7/t 83.9/t 116.3/t 88.1/t
Pre-tax      
NPV8% ($M) 1,210.12 976.76 1,531.80 1,160.45 1,853.47 1,404.14
IRR (%) 36.7% 42.4% 48.0%
After-tax      
NPV8% ($M) 753.17 570.59 955.71 724.03 1,157.08 876.57
IRR (%) 29.2% 33.4% 37.4%
Payback (years) 2.5 years 2.4 years 2.2 years
Combined Phase I and II      
Pre-tax NPV8% ($M) 3,107.81 2,354.40 3,762.18 2,850.13 4,416.60 3,345.91
After-tax NPV8% ($M) 1,969.81 1,492.28 2,384.09 1,806.13 2,797.24 2,119.12

 

 

  1. MINING AND PROCESSING

 

A summary of the revenue, capital costs, production and operating metrics from the Feasibility Study are provided below.

 

  1. PRODUCTION METRICS:

 

Feasibility Study Baseline Production Metrics   LoM
     
Reserve (Mt)   807.0
Processed tonnage (Mtpa)   41.6
Average Fe processing recovery (%)   82.4%
Average mining dilution (%)   1.2%
Average mining ore loss (%)   0.8%
Average recovered concentrate (Mtpa)   15.0
Mine life (years)   20 years

 

 

  1. CAPITAL COSTS:

 

CAPEX Pre-Production   (CA$M) (US$M)
General   28.2   21.4  
Mine – Phase II   37.6   28.5  
Crusher and stockpile   24.3   18.4  
Concentrator   165.0   125.0  
Tailings and water management   50.2   38.0  
Services   30.5   23.1  
Rail and port   73.4   55.6  
Owner’s costs   105.1   79.6  
Contingency (15%)   75.5   57.2  
TOTAL   589.8   446.8  
Deposits   44.0   33.3  
TOTAL Including Deposits   633.8   480.1  

 

 

  1. OPERATING COSTS SUMMARY:

 

Category   LoM (CA$/t) LoM (US$/t)
Mining   13.4   10.2  
Crushing and conveying   1.7   1.3  
Processing plant   7.9   6.0  
Concentrate shipping   16.8   12.7  
Water and tailings management   2.1   1.6  
General and administrative   4.7   3.6  
Total Cash Cost1   46.6   35.4  
Sustainability and other community expenses   1.3   1.0  
Sustaining CAPEX   4.4   3.3  
All-in Sustaining Costs1   52.3   39.7  

 

 

_____________________________
Cash cost and all-in sustaining costs are non-IFRS financial performance measures with no standard definition under IFRS. The Company provides them as supplementary information that management believes may be useful to investors to explain the Company’s financial results.

 

 

  1. KEY ASSUMPTIONS:

 

LoM average gross realized 66.2% Fe Price (CFR China (US$/t) US$84.1/t
Average exchange rate (CA$/US$) 0.758
Diesel price $1.18/l
Electricity tariff $0.0491/kwh

 

 

  1. UPDATED MINE PLAN

 

The Phase II expansion at Bloom Lake continues with the successful operating strategies currently used at the mine since the restart of Phase I. The mining scenario has been updated with operational changes in the pit and new blending constraints required for optimum concentrator productivity.

 

The Phase II mine plan continues with a conventional surface mining method using an owner mining approach. Electric hydraulic shovels will be complemented with front end loaders to allow a flexible mine plan. Additional drilling and hauling capacity will be added as mine tonnages increase starting in January 2021.

 

  1. CONCENTRATOR PLANT

 

Quebec Iron Ore Inc. intends to complete construction of the Phase II concentrator and other supporting assets to bring Bloom Lake’s total average LoM production to 15 Mtpa of 66.2% Fe iron ore concentrate. Existing crushing, feed and concentrate storage facilities will be modified or completed to support operation of both concentrators.

 

The proposed Phase II concentrator plant is based on the currently operating Phase I concentrator which has major proven improvements in terms of tonnage and recovery over historical performances (2010 – 2014). The Phase II recovery circuit is an evolution from the Phase I design and base of the Phase I first year of operation. The main modification from the Phase I design is the addition of a scavenger up current classifier stage that will result in improved recovery and response to feed variations.

 

Major processing equipment is currently on site from the original expansion project that was interrupted in 2012 by Bloom Lake’s previous owner. Much of this equipment will be reused with the exception of the gravity circuit equipment that was used as part of the Phase I restart project. The Phase II project will also benefit from utilization of existing infrastructure and personnel. Overland conveyor, crushers, water management facility and booster pumphouse, workshops, are all examples of existing infrastructure that reduces the overhead burden on the project as well as assists in the development timeline with shorter mobilization periods.

 

  1. LOGISTICS

 

The mine already has an operational rail loop infrastructure, with access to end markets via port and rail. The rail access consists of three separate segments. The first segment, a 31.9 km on-site rail spur, is operational and connects to the Quebec North Shore & Labrador (QNS&L) railway at the Wabush Mines facilities in Wabush, Labrador. The second segment uses the QNS&L railway between Wabush to the Arnaud junction in Sept-Îles. The third segment connects from Arnaud to Pointe-Noire port facilities (Sept-Îles), where the concentrate will be unloaded, stockpiled, then loaded onto vessels for export. Modifications will be made to the rail infrastructure as well as to the stockyard in order to reduce cycle time and increase concentrate storage capacity.

 

Bloom Lake benefits from excellent access to power, water, roads, rail, ports and a highly professional mining labour market, as well as a government that continues to be supportive of new investment and mining.

 

  1. TAILINGS MANAGEMENT

 

Current tailings facilities, combined with the expansion plan set according to the Study, will be utilized to service the additional tonnage from Phase II. While the mine is located on the Canadian shield, being one of oldest and most seismically stable region in the world, the site is designed to resist all extreme scenarios from earthquakes to exceptional rain events. The safe tailings management will continue to adopt world class standards where fine material is separated from coarse material, maximizing each material given their distinct properties and behaviours. This process allows to greatly reduce potentially unstable materials where less than 15% of tailings are categorized as fine material, which are then stored in centerline or downstream construction, considered a proven, safe and stable method for this type of product. To further improve on safety, the dams are raised to levels that cannot exceed 40 metres, while coarse material stored in upstream construction utilizes a slope of 10:1 compared to the industry standard of 6:1. Finally, the Company has a robust monitoring program, including real-time surveillance consoles.

 

  1. FEASIBILITY STUDY AND QUALIFED PERSONS

 

The Feasibility Study will be filed under the Company’s profile on SEDAR within 45 days of the date of this news release. The following Qualified Persons, along with other Qualified Persons, have participated in the preparation of the Feasibility Study:

 

  • André Allaire, P.Eng. – BBA Inc.
  • Isabelle Leblanc, P.Eng. – BBA Inc.
  • Pierre-Luc Richard, P.Geo – BBA Inc.
  • Mathieu Girard, P.Eng. – Soutex
  • Philippe Rio Roberge, P.Eng. – WSP Canada Inc.

 

Each of these foregoing Qualified Persons has reviewed and approved the technical information contained in this news release that is relevant to their area of responsibility and verified the data underlying such technical information. Reference is made to the Feasibility Study that will be filed within 45 days as to the data verification procedures, any limitations thereon and any failure to verify data.

 

  1. MINERAL RESOURCE AND RESERVE ESTIMATES

 

The following table presents the mineral resource for Bloom Lake estimated at a cut-off grade of 15% Fe, inside an optimized open-pit shell based on a long-term iron price of US$61.50 per dry metric tonne (“dmt”) for 62% Fe content, a premium of US$12.7/dmt for the 66.2% Fe concentrate and an exchange rate of 1.24 CA$/US$. The measured and indicated mineral resource for Bloom Lake is estimated at 893.5 Mt with an average grade of 29.3% Fe, and an inferred mineral resource at 53.5 Mt with an average grade of 26.2% Fe. Mineral resources that are not mineral reserves do not have demonstrated economic viability.

 

Mineral Resource Estimate for Bloom Lake (Notes 1-10)

 

 

Classification   Tonnage
(dmt)
  Fe   CaO   Sat   MgO   Al2O3
  kt   %   %   %   %   %
Measured   379,100   30.2   1.4   4.4   1.4   0.3
Indicated   514,400   28.7   2.5   7.7   2.3   0.4
Total M&I   893,500   29.3   2.1   6.3   1.9   0.4
Inferred   53,500   26.2   2.8   8.0   2.4   0.4

 

Notes on mineral resources:
1. The 2019 mineral resource estimate (“MRE”) was prepared by or under the supervision of Pierre-Luc Richard, P. Geo, of BBA Inc. Mr. Richard is an independent qualified person, as defined by NI 43-101 guidelines. The effective date of the estimate is April 19, 2019. CIM definitions and guidelines for Mineral Resource Estimates have been followed.
2. These mineral resources are not mineral reserves as they do not have demonstrated economic viability. The MRE presented herein is categorized as measured, indicated, and inferred resources. The quantity and grade of reported Inferred resources in this MRE are uncertain in nature and there has been insufficient exploration to define these Inferred resources as Indicated or Measured.
3. Resources are presented as undiluted and in situ for an open-pit scenario and are considered to have reasonable prospects for economic extraction. The constraining pit shell was developed using pit slopes varying from 42 to 46 degrees. The pit shell was prepared using Minesight.
4. The MRE was prepared using GEOVIA Surpac 2019HF1 v.7.0.1949.0 and is based on 569 surface drill holes (141,289m), and a total of 11,397 assays.
5. Density values were calculated based on the formula established and used by the issuer.
6. Grade model resource estimation was calculated from drill hole data using an Ordinary Kriging interpolation method in a block model using blocks measuring 10 m x 10 m x 14 m (vertical) in size.
7. The estimate is reported using a cut-off grade of 15% Fe. The MRE was estimated using a cut-off grade of 15% Fe, inside an optimized open pit shell based on a long-term iron price of US$61.50/dmt for 62% Fe content, a premium of US$12.7/dmt for the 66.2% Fe concentrate and an exchange rate of 1.24 CA$/US$.
8. Calculations used metric units (metre, tonne). Metal contents are presented in percent. Metric tonnages were rounded and any discrepancies in total amounts are due to rounding errors.
9. The author is not aware of any known environmental, permitting, legal, title-related, taxation, socio-political or marketing issues, or any other relevant issues not reported in this Feasibility Study, that could materially affect the Mineral Resource Estimate.
10. Mineral reserves stated below are included in the mineral resources.

 

 

The proven and probable mineral reserve is estimated at 807.0 Mt at an average grade of 29.0% Fe based on a cut-off grade of 15% Fe. The mineral reserve was estimated using a long-term concentrate price of US$60.89/dmt for 62% Fe content, a premium of US$12.7/dmt for the 66.2% Fe concentrate and an exchange rate of 1.24 CA$/US$. The mineral reserve includes a mining dilution and ore loss calculated on a block-by-block basis based on the neighbouring blocks lithology and grade. The average strip ratio of the open pit is 0.88.

 

Mineral Reserve Estimate (Notes 1-13)

 

 

Classification   Diluted Ore
Tonnage
(dmt) Mt
  Fe %   CaO %   Sat %   MgO %   Al2O3 %
Proven   346.0   29.9   1.5   4.7   1.4   0.3
Probable   461.0   28.2   2.6   7.9   2.5   0.6
Total P&P   807.0   29.0   2.2   6.5   2.0   0.5

 

Notes on mineral reserves:
1. The mineral reserves were estimated using the Canadian Institute of Mining, Metallurgy and Petroleum (CIM) Standards for Mineral Resources and Reserves, Definitions and Guidelines prepared by the CIM Standing Committee on Reserve Definitions and adopted by CIM Council May 10th, 2014.
2. The mineral reserve estimate was prepared by or under the supervision of Isabelle Leblanc, P. Eng., from BBA. Ms. Leblanc is an independent and qualified person, as defined by NI 43-101. The effective date of the estimate is May 17, 2019.
3. Inside the final open pit design all the measured resources and associated dilution (waste material at 0% Fe) have been converted into Proven Mineral Reserves. Inside the final open pit design all the indicated resources and associated dilution (waste material at 0% Fe) have been converted into Probable Mineral Reserves.
4. Mineral reserves based on forecasted December 31, 2020 mining surface.
5. The reference point of the mineral reserve is the primary crusher feed.
6. Mineral reserves are estimated at a cut-off grade of 15% Fe.
7. Mineral reserves are estimated using a long-term iron price reference price (P62) of US$60.89/dmt and an exchange rate of 1.24 CA$/US$. An Fe concentrate price adjustment of US$12.70/dmt was added.
8. Bulk density of ore is variable but averages 3.40 t/m3.
9. The average strip ratio is 0.88:1.
10. Ore loss and dilution were calculated using a 1m contact skin between ore and waste rock types.
11. Average mining dilution is 1.2% at a grade of 0% Fe. Dilution was applied block by block and shows a wide range of local variability.
12. The average ore loss is 0.8% at a grade of 31% Fe. Ore loss was applied block by block and shows a wide range of local variability.
13. The author of the Feasibility Study is not aware of any known environmental, permitting, legal, title-related, taxation, socio-political or marketing issues, or any other relevant issues not reported in the Feasibility Study, that could materially affect the Mineral Reserve Estimate.

 

 

About the Bloom Lake Mining Complex

 

On April 11, 2016, Champion, through its subsidiary Quebec Iron Ore Inc., acquired the Bloom Lake assets from affiliates of Cliffs Natural Resources Inc. that were subject to restructuring proceedings under the Companies’ Creditors Arrangement Act (Canada). Following the release of a feasibility study on February 16, 2017, Champion recommissioned Bloom Lake in February 2018, which completed its first shipment on April 1, 2018. QIO is 63.2% owned by Champion, with the remaining 36.8% equity interest owned by Ressources Québec, acting as a mandatary of the Government of Quebec. On May 29, 2019, Champion concluded an agreement with Ressources Québec to acquire 100% of the property.

 

The Bloom Lake property is located on the south end of the Labrador Trough, approximately 13 km north of Fermont, Quebec, and 10 km north of the Mount-Wright iron ore mining operation of ArcelorMittal Mines Canada. The mine is an open-pit truck and shovel operation with a concentrator. From the site, iron concentrate is transported by rail, initially on the Bloom Lake Railway, to a ship loading port in Sept-Îles, Quebec.

 

About Champion Iron Limited

 

Champion is a producing iron development and exploration company, focused on developing its significant iron resources in the south end of the Labrador Trough in the province of Québec. Following the acquisition of its flagship asset, the Bloom Lake iron ore property, the Company implemented upgrades to the mine and processing infrastructure and has partnered in projects associated with improving access to global iron markets, including rail and port infrastructure initiatives with government and other key industry and community stakeholders. Champion’s management team includes professionals with mine development and operations expertise, who also have vast experience from geotechnical work to green field development, brown field management including logistics development and financing of all stages in the mining industry.

 

Posted June 20, 2019

Share this news article

MORE or "UNCATEGORIZED"


Alamos Gold Announces Friendly Acquisition of Argonaut Gold

Unlocking Value Through the Creation of One of Canada’s Lar... READ MORE

March 27, 2024

Foremost Lithium Reports Widest Intercept to Date; 32.53 Metres of Spodumene-Bearing Pegmatite at its Zoro Lithium Project in Manitoba, Canada

Highlights Include: Drill hole FL 24-009 intersected 32.53 metres... READ MORE

March 27, 2024

WESTERN COPPER AND GOLD ANNOUNCES METALLURGICAL PROGRAM AND ASSOCIATED DRILL RESULTS

Western Copper and Gold Corporation (TSX: WRN) (NYSE American: WR... READ MORE

March 27, 2024

Endeavour Reports Strong FY-2023 Results

ENDEAVOUR REPORTS STRONG FY-2023 RESULTS Production of 1.1Moz at AISC of... READ MORE

March 27, 2024

Orezone Reports 2023 Year-end and Q4 Results, and Provides 2024 Guidance

Orezone Gold Corporation (TSX: ORE) (OTCQX: ORZCF) reported its o... READ MORE

March 27, 2024

Copyright 2024 The Prospector News