Aya Gold & Silver Announces First Silver Pour at Expanded Zgounder Mine

Aya Gold & Silver Inc. (TSX: AYA) (OTCQX: AYASF) is pleased to announce the first silver pour from its expanded Zgounder Mine in the Kingdom of Morocco. The first silver pour was completed on November 27, 2024.

 

Highlights

  • The first full silver pour was completed on November 27, 2024: 
    • First silver pour achieved from the new mill throughout the entire circuit.
    • Hot commissioning is now complete with the gravity circuit currently being commissioned.
    • Recoveries of over 80% recorded and improving:
      • Improvement as the circuit stabilises and mill head grade increases.
      • The mill is currently being fed with marginal ore to minimize silver lost through ramp up.
    • All equipment / circuits are operating as expected.
  • Operations ramping up: 
    • Nameplate of 2,000 tonnes per day (“tpd”) was achieved on November 29, 2024, less than a month after first ore in mill.
    • Availability, recovery and throughput continue to improve daily, reinforcing our confidence in reaching commercial production before end of year.

“This milestone brings us closer to the start of commercial production at our expanded Zgounder mill in the coming weeks and marks our transition into a tier-one, pure-play, and profitable silver producer,” said Benoit La Salle, President & CEO. “I am incredibly proud of our team’s hard work and extend my sincere thanks to everyone who contributed to the successful, on-budget completion of this expansion. With a full ramp-up planned for next year, we are encouraged by the strong operating indicators, overall performance, and continued optimization of our deposit.”

 

Figure 1: First Silver Doré Bars

About Aya Gold & Silver Inc.

Aya Gold & Silver Inc. is a rapidly growing, Canada-based silver producer with operations in the Kingdom of Morocco.

The only TSX-listed pure silver mining company, Aya operates the high-grade Zgounder Silver Mine and is exploring its properties along the prospective South-Atlas Fault, several of which have hosted past-producing mines and historical resources. Aya’s Moroccan mining assets are complemented by its Tijirit Gold Project in Mauritania, which, subject to the announcement of September 12, 2024, will be developed by Mx2 Mining, a new spinout gold-growth company.

Aya’s management team has been focused on maximizing shareholder value by anchoring sustainability at the heart of its operations, governance, and financial growth plans.

Posted December 2, 2024

Share this news article

MORE or "UNCATEGORIZED"


Gold Candle to Acquire Pan American Silver’s Larder Property, Further Enhancing Its Presence in the Abitibi

Acquisition Adds Indicated Gold Resources of 388koz and Inferred ... READ MORE

May 8, 2026

Scorpio Gold Drills 0.62 G/T Gold Over 62.21 Metres From 230.43 Metres Within Manhattan Caldera, at Black Mammoth

Highlights • Hole 26MN-069 returned: o 0.62 g/t gold over 62.21... READ MORE

May 8, 2026

Wheaton Precious Metals Announces Record Revenue, Earnings and Cash Flow for the First Quarter of 2026

“Wheaton delivered a strong start to 2026, with Salobo and... READ MORE

May 8, 2026

Vior Gold Corporation Intersects 12.8 g/t Au Over 2.0 Meters and 5.45 g/t Au Over 3.0 Meters

VIOR GOLD CORPORATION INC. (TSX-V: VIO) (OTCQB: VIORF) (FRA: VL5)... READ MORE

May 7, 2026

One Bullion Reports Gravity-Finish Assay Results at Vumba Project, Including 30.8 g/t Au, and Receives EIA Approval for Maitengwe Project

Gravity-Finish Re-Assay Confirms High-Grade Gold Mineralization a... READ MORE

May 7, 2026

Copyright 2026 The Prospector News