Atico Produces 2.08 Million Pounds of Cu and 1,465 Ounces of Au in Second Quarter 2026

You have opened a direct link to the current edition PDF

Open PDF Close
Uncategorized

Share this news article

Atico Produces 2.08 Million Pounds of Cu and 1,465 Ounces of Au in Second Quarter 2026

 

 

 

 

 

Atico Mining Corporation (TSX-V: ATY) (OTCIQ: ATCMF) announces its operating results for the three months ended June 30, 2026 from its El Roble mine. Production for the quarter totaled 2.08 million pounds of copper and 1,465 ounces of gold in concentrates.

 

“The El Roble mine performed as planned during this period and delivered incremental improvements compared to the first quarter, particularly in copper grades and metal recovery. Gold grade as well as output were impacted as we temporarily mine through a lower gold grade zone of the deposit,” said Fernando E. Ganoza, CEO. “In the second half of the year, we are targeting an updated reserve report and anticipate further gains in production as we optimize new operational equipment, gaining further access to higher-grade ore zones.”

 

Second Quarter Operational Highlights

  • Production of 2.08 million pounds of copper contained in concentrates; a decrease of 4% over Q2 2025.
  • Production of 1,465 ounces of gold contained in concentrates; a decrease of 38% over Q2 2025.
  • Average processed tonnes per day of 786, a decrease of 5% over Q2 2025.
  • Copper head grade of 1.91%, an increase of 10% over Q2 2025.
  • Gold head grade of 1.25 grams per tonne; a decrease of 40% over Q2 2025.
  • Copper and gold recovery of 92.3% and 68%; no significant change for copper and an increase of 18% for gold, respectively, over Q2 2025.

 

Second Quarter Operational Details

 

  Q2 2026
Total
  Q2 2025
Total
  % Change  
Production (Contained in Concentrates)            
Copper (000s pounds) 2,081   2,155   -4 %  
Gold (ounces) 1,465   2,385   -38 %  
Mine            
Tonnes of ore mined 53,156   60,633   -12 %  
Mill            
Tonnes processed 53,585   62,007   -14 %  
Tonnes processed per day 786   830   -5 %  
Copper grade (%) 1.91   1.74   10 %  
Gold grade (g/t) 1.25   2.08   -40 %  
Recoveries            
Copper (%) 92.3   91.2   1 %  
Gold (%) 68.0   57.6   18 %  
Concentrates            
Copper and Gold Concentrates (dmt) 5,332   5,592   -5 %  
             
Payable copper produced (000s lbs) 1,951   2,032   -4 %  
 
Note: Metal production figures are subject to adjustments based on final settlement. The reported results are preliminary in nature and are awaiting independent lab verification.
 

 

Concentrate Inventory

 

The number of shipments the Company can export in any given quarter depends on several variables some of which the Company does not control, hence there may be an inherent variability in tonnes shipped quarter to quarter.

 

 

  Q2 2026    
Amounts in dry metric tonnes    
Opening inventory 1,266    
Production 5,332    
Sales -4,989    
Adjustments (118 )  
Closing inventory 1,491    
Number of shipments 1    
 
Note: Concentrate figures are subject to adjustments based on final surveys and final settlement of sales.
 

El Roble Mine

 

The El Roble mine is a high grade, underground copper and gold mine with nominal processing plant capacity of 1,000 tonnes per day, located in the Department of Choco in Colombia. Its commercial product is a copper-gold concentrate.

 

Since obtaining control of the mine on November 22, 2013, Atico has upgraded the operation from a historical nominal capacity of 400 tonnes per day.

 

El Roble’s reserves estimate, with an effective date of March 12, 2024, includes Proven and Probable mineral reserves of 828 thousand tonnes averaging 2.49% Cu, 2.20 g/t Au and a life of mine until Q1-2027. A full NI 43-101 technical report is available on SEDAR+. For more information on the reserves estimate refer to SEDAR+ and on the Company’s website.

 

Mineralization is open at depth and along strike and the Company plans to further test the limits of the deposit. On the larger land package, the Company has identified a prospective stratigraphic contact between volcanic rocks and black and grey pelagic sediments and cherts that has been traced by Atico geologists for ten kilometers. This contact has been determined to be an important control on VMS mineralization on which Atico has identified numerous target areas prospective for VMS type mineralization occurrence, which is the focus of the current surface drill program at El Roble.

 

Qualified Person

 

Mr. Thomas Kelly (SME Registered Member 1696580), advisor to the Company and a qualified person under National Instrument 43-101 standards, is responsible for ensuring that the technical information contained in this news release is an accurate summary of the original reports and data provided to or developed by Atico.

 

About Atico Mining Corporation

 

Atico is a growth-oriented Company, focused on exploring, developing and mining copper and gold projects in Latin America. The Company generates significant cash flow through the operation of the El Roble mine and is developing its high-grade La Plata VMS project in Ecuador. The Company is also pursuing additional acquisition of advanced stage opportunities.

 

Posted August 7, 2026

Share this news article

MORE or "UNCATEGORIZED"


Heliostar Presents Q2 2026 Financial and Operating Results with Record Gold Production and Cash Balance

Q2 2026 Highlights: Produced a record 14,803 gold ounces and 79,7... READ MORE

August 7, 2026

Galiano Gold Reports Second Quarter 2026 Results

Maintains Full-Year 2026 Guidance and Advances Key Growth Priorit... READ MORE

August 7, 2026

Lundin Gold Reports Second Quarter 2026 Results

Strong Quarterly Earnings and Continued Significant Shareholder R... READ MORE

August 7, 2026

Perpetua Resources Reports New High-Grade Gold and Antimony Discoveries and a New Gold-Tungsten Zone at Stibnite

First exploratory drilling in nearly a decade at Perpetua’s... READ MORE

August 7, 2026

Torex Gold Reports Q2 2026 Results

Strong free cash flow and 46% AISC margin support continued capit... READ MORE

August 7, 2026

Copyright 2026 The Prospector News