Americas Gold and Silver Corporation (TSX: USA) (NYSE American: USAS) a growing North American precious metals producer, reports consolidated financial and operational results for the quarter ended June 30, 2023.
This earnings release should be read in conjunction with the Company’s Management’s Discussion and Analysis, Financial Statements and Notes to Financial Statements for the corresponding period, which have been posted on the Americas Gold and Silver Corporation SEDAR profile at www.sedar.com, and on its EDGAR profile at www.sec.gov, and which are also available on the Company’s website at www.americas-gold.com. All figures are in U.S. dollars unless otherwise noted.
Highlights
“Production in the second half of the year is expected to be higher than the first half of the year and the Company remains on track to meet its 2023 production guidance,” stated Americas President and CEO Darren Blasutti. “The Company has also made the decision to source higher-grade silver copper ore from the EC120 deposit at the Cosalá operations, starting later this month. The decision is a result of expected higher silver and copper prices relative to zinc prices going forward. Developing into the EC120 deposit allows for greater revenue optimization to constantly changing metal prices and increases silver optionality.”
Cosalá Operations
The Cosalá Operations produced approximately 335,000 ounces of silver, 3.2 million pounds of lead and 9.6 million pounds of zinc in Q2-2023, compared to approximately 128,000 ounces of silver, 3.9 million pounds of lead and 9.9 million pounds of zinc in Q2-2022, benefitting from more production from the higher-grade silver areas in the Upper Zone of the San Rafael mine. Cash cost and all-in sustaining cost were $4.51 per silver ounce and $11.10 per silver ounce, respectively, which were negatively impacted in the quarter by lower lead and zinc prices and an appreciation in the Mexican peso compared with Q2-2022.
Silver production from the Cosalá Operations in 2023 is expected to be between 1.2 – 1.4 million ounces, benefitting from more production from the higher-grade silver areas in the Upper Zone of the San Rafael mine and starting to source higher grade silver ore from the EC120 deposit starting later this month. The decision is a result of lower-than-expected zinc prices and expected higher silver prices going forward. Developing into the EC120 deposit allows for greater revenue optimization to constantly changing metal prices and increases silver optionality.
Galena Complex
Attributable production from the 60% owned Galena Complex was approximately 238,000 ounces of silver and 2.7 million pounds of lead in Q2-2023, compared to approximately 171,000 ounces of silver and 2.5 million pounds of lead in Q2-2022. Much of the increase in silver production comes from the 3700 Level silver-copper areas which drove total silver grade processed above 400 g/t during the quarter. Cash cost and all-in sustaining cost were $17.74 per silver ounce and $24.74 per silver ounce, respectively, a decrease in both cash cost and all-in sustaining cost compared to Q2-2022. All-in sustaining cost per silver ounce at the Galena Complex is anticipated to continue to decrease with the completion of the Galena Hoist project as the benefits of scaling economies on the existing cost base are realized.
During the quarter, the Company successfully installed the Galena Hoist and it is now operational. The Company is focused on finishing the remaining shaft repair work, which is not expected to impact production guidance for the Galena Complex in 2023. The Company has fully inspected the shaft with a LIDAR survey showing less than a few hundred feet of the shaft requiring more extensive repair. These repairs are on-going and are expected to be completed in Q4-2023. The Galena Hoist will support plans to increase production, improve operational flexibility and improve operational economics.
About Americas Gold and Silver Corporation
Americas Gold and Silver Corporation is a high-growth precious metals mining company with multiple assets in North America. The Company owns and operates the Cosalá Operations in Sinaloa, Mexico, manages the 60%-owned Galena Complex in Idaho, USA, and is re-evaluating the Relief Canyon mine in Nevada, USA. The Company also owns the San Felipe development project in Sonora, Mexico.
Technical Information and Qualified Persons
The scientific and technical information relating to the Company’s material mining properties contained herein has been reviewed and approved by Daren Dell, P.Eng., Chief Operating Officer of the Company. The Company’s current Annual Information Form and the NI 43-101 Technical Reports for its mineral properties, all of which are available on SEDAR at www.sedar.com, and EDGAR at www.sec.gov, contain further details regarding mineral reserve and mineral resource estimates, classification and reporting parameters, key assumptions and associated risks for each of the Company’s material mineral properties, including a breakdown by category.
All mining terms used herein have the meanings set forth in National Instrument 43-101 – Standards of Disclosure for Mineral Projects (“NI 43-101”), as required by Canadian securities regulatory authorities. These standards differ from the requirements of the SEC that are applicable to domestic United States reporting companies. Any mineral reserves and mineral resources reported by the Company in accordance with NI 43-101 may not qualify as such under SEC standards. Accordingly, information contained in this news release may not be comparable to similar information made public by companies subject to the SEC’s reporting and disclosure requirements.
Search Minerals Inc. (TSX-V: SMY) is pleased to announce that i... READ MORE
New Found Gold Corp. (TSX-V: NFG) (NYSE-A: NFGC) is pleased to re... READ MORE
GoldHaven Resources Corp. (CSE: GOH) (OTCQB: GHVNF) (FSE: 4QS0) ... READ MORE
Eldorado Gold Corporation (TSX: ELD) (NYSE: EGO) reports the Comp... READ MORE
Centerra Gold Inc. (TSX: CG) (NYSE: CGAU) reported its third quar... READ MORE