Abcourt Mines Inc. (TSX-V: ABI) (OTCQB: ABMBF) is pleased to announce results from the underground diamond drilling campaign at the Sleeping Giant mine.
As part of the optimization of the mining plan with a view to support a prefeasibility study and starting production, Abcourt has carried out, from December 2023 to July 31, 2024, 33 underground drilling holes totaling 3,650 meters.
According to the mining plan, the Zone 20 West stope is among the first stopes to be put into production at start-up. 11 holes totaling 1,118 metres were drilled in the Zone 20 West sector to better define the dimension and grade of the planned stope.
Abcourt presents the results of 6 drill holes totaling 641 meters drilled in Zone 20 West from level 235. The 5 other holes drilled in the sector are awaiting results.
The highlights of the analysis results, included in this press release, are as follows:
The main results are displayed in Table 1:
Table 1: Main Underground Drilling Results from Zone 20 West |
|||||||
Drilling | From | To | Interval | Au | Vein | Notes | |
(m) | (m) | (m) | (g/t) | ||||
23-485 | 57.4 | 58.4 | 1,00 | 46.07 | vein 1 | ||
23-486 | No significant results | western limit of the stope | |||||
23-487 | 19.5 | 22.1 | 2.6 | 6.71 | vein 2 | ||
Including | 19.5 | 20.1 | 0.6 | 16.97 | |||
and | 64.3 | 64.8 | 0.5 | 7.4 | vein 1 | western limit of the stope | |
23-488 | No significant results | western limit of the stope | |||||
23-489 | 19,00 | 20,00 | 1,00 | 7.19 | vein 2 | ||
and | 62,00 | 62.5 | 0.5 | 125.67 | vein 1 | ||
23-490 | No significant results | western limit of the stope | |||||
Notes: |
|||||||
1. The length represents the length measured along the drill core. | |||||||
2. Assay results are not capped, but higher-grade sub-intervals are highlighted. |
The main results from the holes drilled at Zone 20 West are illustrated in a longitudinal section (Figure 1).
Figure 1: Zone 20 West, Longitudinal Section.
Drilling data shows that:
It is also important to note the presence of a second vein (vein 2) subparallel to vein 1, located 30 m north of it (see figure 2). This vein has been intercepted by several drill holes. The most interesting intercepts are:
The extension of vein 2 is to be tested, particularly towards the west.
Figure 2: Zone 20 West, Plan View Level 235.
The drilling campaign in Zone 20 West has been completed. We are awaiting the results of the last drill holes to finalize the interpretation and three-dimensional modeling of the planned stope. Drilling operations continue underground at level 235 in Zone 3 South.
Mohamed Haithem Bennia, Superintendent Geology at the Sleeping Giant mine, comments: “With a view to continuously optimizing our production ramp up, we are continuing our drilling and modeling work for our future stopes. This approach is the best way to ensure tonnes of quality to supply our mill while respecting deadlines and extraction objectives towards commercial production.”
Quality Control Measures
The drilling, core description and analysis preparation work was carried out under the supervision of Mohamed Haithem Bennia, geo, superintendent geology, qualified person according to Regulation 43-101.
Following an analytical quality assurance and control program, blank samples and certified reference materials as well as duplicates were added among the core samples before being analyzed.
The half-cores were prepared at the Sleeping Giant mine’s in-house laboratory according to industry standards.
To reduce the time taken to receive analysis results, part of the batch of samples used in the preparation of this press release was sent, in the form of pulps, to an external laboratory and the other part was analyzed at the internal laboratory of the Sleeping Giant mine.
The samples analyzed in the internal laboratory were carried out by fire analysis (A.A.) with atomic absorption finishing. Samples with a grade greater than 10g/t Au were reanalyzed with a gravimetric finish.
In order to validate the quality of analysis of the internal laboratory, reanalysis were produced by Techni-Lab S.G.B. Abitibi inc. division of ActLabs which is an accredited external laboratory, registered to ISO 9001 and ISO/IEC 17025 certified CCN (lab707), MELCC (lab375) located in Sainte-Germaine-Boulé, Quebec.
The audits show a high degree of correlation with internal laboratory results.
The samples sent externally were analyzed by the MSALABS laboratory in Val-d’Or, Quebec, using the Photon AssayTM method. MSA operates numerous laboratories around the world and maintains ISO-17025 accreditation for many metal determination methods. MSA is an ISO-17025 accredited laboratory for the photonic analysis method.
Qualified Persons
Mohamed Haithem Bennia, geo, superintendent geology of the Sleeping Giant mine, wrote, collected, verified and approved the technical information contained in this press release.
Pascal Hamelin, Eng, President and Chief Executive Officer of the Corporation, has verified and approved the technical information contained in this press release.
Mr. Hamelin and Mr. Bennia are qualified persons under Regulation 43-101.
ABOUT ABCOURT MINES INC.
Abcourt Mines Inc. is a Canadian gold exploration Corporation with properties strategically located in northwestern Quebec, Canada. Abcourt 100% owns the Sleeping Giant mill and mine where it concentrates its activities. The Sleeping Giant mine has a mining lease, as well as environmental certificates of authorization to extract up to 750 tonnes per day from its underground mine.
Red Pine Exploration Inc. (TSX-V: RPX) (OTCQB: RDEXF) is pleased ... READ MORE
F3 Uranium Corp. (TSX-V: FUU) (OTC Pink: FUUFF) is pleased to ann... READ MORE
Collective Mining Ltd. (NYSE: CNL) (TSX: CNL) is pleased to ann... READ MORE
Aris Mining Corporation (TSX: ARIS) (NYSE-A: ARMN) announces t... READ MORE
Staffing in place and operations shakedown underway Rare E... READ MORE