The Prospector News

1911 Gold Delivers Positive PEA for True North Highlighting Robust Economics with Low Capital Intensity and High Returns

You have opened a direct link to the current edition PDF

Open PDF Close
Uncategorized

Share this news article

1911 Gold Delivers Positive PEA for True North Highlighting Robust Economics with Low Capital Intensity and High Returns

 

 

 

 

 

1911 Gold Corporation (TSX-V: AUMB) (OTCQX: AUMBF) (FRA: 2KY) is pleased to announce significant positive results from the independent Preliminary Economic Assessment for the True North Gold Project, located in southeastern Manitoba, Canada. The PEA was prepared by AMC Mining Consultants (Canada) Ltd. in accordance with National Instrument 43-101 Standards of Disclosure for Mineral Project, with all financial figures expressed in Canadian Dollars unless otherwise stated.

 

The PEA outlines a robust gold mining operation utilizing the fully built and permitted infrastructure, including shafts, underground workings, and the processing and tailings management facility. 1911 Gold has estimated the infrastructure replacement value as being in excess of $400 million. The plan targets steady-state production of 58,114 ounces per annum with a mine life of 11 years.

 

PEA Highlights:

  • Robust Economics (After-tax):  Net present value (5%) of $391 million, internal rate of return of 105%, and a payback period of 2.2 years at a long-term gold price of US$3,000 per ounce; at a constant gold price of US$4,800/oz, the NPV is $998 million, no calculated IRR due to no years with a negative cash flow, and an almost immediate payback period of 1.0 year.
  • Production Profile: Steady-state production profile of 1,215 tonnes per day for average payable gold production of 58,100 oz per annum (Years 3-8) with an 11-year life of mine.
  • LOM Cash Flow: Total payable gold production of 527,100 oz LOM with the current mineral resources, generating $545 million undiscounted after-tax free cash flow1 and generating 326 full-time jobs.
  • Fully Permitted, Low Capital Project: Initial capital expenditures of $59.2 million, utilizing the currently built and permitted payable infrastructure. Additional Capex of $46.7 million during the first 2 years of ramp-up, and $367.2 million of sustaining capital over LOM with a high profitability index of 6.6 and low peak investment of $59.2 million in Year 1.
  • Processing: Average diluted mill head grade of 4.32 grams per tonne gold with gold recoveries of 93.5% over the LOM.
  • Cash Costs and AISC1: Producing gold at a cash cost of US$1,390/oz and all in sustaining cost of US$1,897/oz.
  • Near-Term Production: Production due to start in the first half of 2027 (“H1 2027“) with test mining planned for the second half of 2026 (“H2 2026“).
  • Production Growth: 1911 Gold has identified excellent potential to increase production by developing recently discovered zones such as San Antonio Southeast, San Antonio West, and Shore which are adjacent to existing infrastructure and not included in the study, in addition to regional targets.

 

1. AISC and Free Cash Flow are non-IFRS financial measures and have no standardized meaning under IFRS Accounting Standards (“IFRS”), and may not be comparable to similar measures used by other issuers.

 

“The delivery of this PEA marks another defining moment for 1911 Gold, outlining a highly efficient, low-capital path to the first phase of production with robust economics and exceptional returns,” stated Shaun Heinrichs, President and Chief Executive Officer of 1911 Gold. “This plan leverages existing infrastructure and a mining strategy suited to the ore body, significantly reducing the project’s capital intensity and technical hurdles that challenged previous operators. Our staged development approach provides a disciplined roadmap to ramp up operations toward an initial steady-state production. This PEA proves that True North is not just a restart story, but is the cornerstone of a district-scale gold project in one of Canada’s premier mining jurisdictions.”

 

Eric Vinet, Chief Operating Officer of 1911 Gold, stated “This PEA outlines a foundational plan to restart operations at True North by optimizing existing infrastructure and confirms the economic viability of a safe and efficient multi-mine operation. Beyond the scope of this study, we see significant potential to further optimize these economics by establishing a centralized ‘super-level’ on Level 16. By connecting the adjacent zones at Hinge, 007, and, potentially, Cohiba directly to the True North Main Shaft, we can transition to a gravity-fed, horizontal haulage model. The proximity of these zones – notably Hinge, located within 100 m of existing infrastructure – supports the technical rationale for centralized hoisting, which has the potential to materially reduce operating costs.”

 

True North PEA Overview

 

Table 1: Summary of True North Project Economics

 

General  Unit  LOM Total / Avg.
Gold price assumption (Long Term) per ounce US$3,000
Gold price assumption (2027) per ounce US$3,500
Gold Price assumption (2028) per ounce US$3,200
Exchange rate ($US:$CAD) 0.72
Mine life years 11
Total mill feed tonnes 4,066,000
Average diluted grade (LOM) g/t Au 4.32
Economics (pre-tax)  Unit  LOM Total / Avg.
Net present value (NPV 5%) millions 526.7
Internal rate of return (IRR) % 118 %
Payback years 2.2
LOM avg. annual cash flow millions 67.1
LOM cumulative cash flow millions 732.8
Steady State (yrs 3-8) avg. annual cash flow millions 93.0
Economics (after-tax)  Unit   LOM Total / Avg.
Net present value (NPV 5%) millions 390.6
Internal rate of return (IRR) % 105 %
Payback years 2.2
LOM avg. annual cash flow millions 48.9
LOM cumulative cash flow millions 544.5
Steady Sate (yrs, 3-8) avg. annual cash flow millions 68.2
Profitability index (NPV/initial capital) ratio 6.6
Peak investment (Annual) millions 59.2
Production  Unit  LOM Total / Avg.
Mill head grade g/t Au 4.32
Mill head grade (years 2029-2034) g/t Au 4.40
Mill recovery rate (average LOM) % 93.5 %
Average mining rate (years 2029-2034) tpd 1,215
Production cont…  Unit  LOM Total / Avg.
Average annual gold production LOM ounces 47,945
Average gold production (years 2029-2034) ounces 58,114
Peak grade (year 2031) g/t Au 4.70
Peak gold production (year 2031) ounces 61,327
Total LOM recovered gold ounces 527,400
Operating Costs  Unit  LOM Total / Avg.
Mining cost $/t milled 175
Processing cost $/t milled 38
G&A cost $/t milled 37
Total operating costs $/t milled 250
Refining & transport cost $/oz 3.17
Royalty NSR % 0 %
Cash costs* US$/oz 1,390
AISC** US$/oz 1,897
Capital Costs  Unit  LOM Total / Avg.
Initial capital millions 59.2
Pre-commercial production capital millions 46.7
Sustaining capital millions 367.2
Closure costs millions 7.3
Salvage value millions 2.3
 

Notes

* Cash costs consist of mining costs, processing costs, mine-level general & administrative expenses and refining charges and royalties.
** AISC includes cash costs plus sustaining capital, closure cost and salvage value.

 

The PEA is preliminary in nature, includes inferred Mineral Resources that are considered too speculative geologically to have economic considerations applied to them that would enable them to be categorized as Mineral Reserves, and there is no certainty that the PEA will be realized. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability.

 

Sensitivities

 

1911 Gold has conducted a sensitivity analysis using the PEA financial model on the base case pre-tax and after-tax NPV and IRR of the Project, using the following variables: metal price, initial capex, total operating costs, and foreign exchange. Table 2 shows the after-tax sensitivity analysis results at various long term gold price assumptions.

 

As shown in Table 3 and Table 4, the sensitivity analysis revealed that the project is most sensitive to changes in gold prices, and foreign exchange and less sensitive to capital and operating costs.

 

 

Table 2: After-Tax Sensitivity Summary
Gold Price

(US$/oz)

$2,000 $2,600 $3,000

Long-term

(Base Case)

$3,800 $4,800 $5,500
After-tax NPV(5%), millions ($41) $247 $391 $665 $998 $1,237
IRR -1.3 % 50.0 % 105.3 % 611.0 % NA*  NA*
Profitability index -0.7 4.2 6.6 11.2 16.9 20.9
Payback (years) 17.0 4.4 2.2 1.2 0.9 0.7
Notes:
* There are no years with negative cash flow to calculate an IRR

 

 

Table 3: After-Tax NPV5% Sensitivity
Gold Price After-Tax NPV5% Initial CAPEX
(CAD$M)
Total OPEX
($CADM))
FX (CAD$M)
(US$/oz) (Base Case) (-25 %) (+25 %) (-25 %) (+25 %) (-25 %) (+25 %)
$2,000 ($41) ($5) ($82) $140 ($233) ($322) $213
$2,600 $247 $283 $204 $371 $95 ($67) $476
$3,000 $391 $426 $348 $506 $268 $92 $647
$3,600 $595 $631 $552 $712 $478 $281 $902
$4,000 $731 $767 $688 $1,012 $785 $391 $1,066
$4,700 $971 $1,007 $928 $1,081 $853 $570 $1,365

 

 

 

Table 4: After-Tax IRR Summary
Gold Price After-Tax IRR Initial CAPEX (CAD$M) Total OPEX (CAD$M) FX (CAD$M)
(US$/oz) (Base Case) (-25 %) (+25 %) (-25 %) (+25 %) (-25 %) (+25 %)
$2,000 -2 % 4 % (6 %) 28 %  NA*  NA* 41 %
$2,600 50 % 98 % 31 % 99 % 20 % (6 %) 167 %
$3,000 105 % 420 % 58 % 214 % 55 % 19 % 516 %
$3,600 341 % NA*  119 % 1,813 % 159 % 60 % NA*
$4,000 1727 % NA* 189 % NA* 349 % 105 % NA*
$4,700  NA*  NA* 595 % NA* NA* 289 % NA*
Notes:
* There are no years with negative cash flow to calculate an IRR

 

Mining

 

The True North Gold Project will consist of underground mining extraction via four access points: the Main “A” Shaft, the Hinge decline, the Cohiba decline and later the SG-1 decline. Initial mining and development will be through the Main “A” shaft, providing access to Level 16 (-695 metres) and Level 26 (-1,145 metres), and the Hinge decline, maximizing current underground development to accelerate development and minimize initial capital costs. The initial plan for the development is to ramp up to a steady-state daily production rate of 1,215 tpd (from years 3-8).

 

The mineral deposits and zones used in the mine plan are contained in a number of deposit areas over a lateral distance of over 4,500 metres and down to depths of over 1,450 m below surface through a series of winzes and internal declines. The deposits are all amenable to underground mining using longitudinal long-hole open stope mining methods, with minimum dimensions of 25 m long by 1.5 m wide by 18 m high between sublevels, assuming 15% dilution with no gold grade and 97% mining recovery. The mining cycle will incorporate a strategic backfill plan, utilizing development waste rock to fill depleted stopes. This will enhance ground stability and significantly reduce operating costs by minimizing the volume of waste material required to be hoisted to surface, thereby optimizing available shaft capacity for high-grade ore.

 

A total of 4,066,000 tonnes at an average diluted grade of 4.32 g/t Au will be extracted under the current proposed plan for a total of 527,100 oz of payable gold produced.

 

Table 5: Mining Areas and Projected Production*

 

Access Deposit Tonnes Grade Ounces
Shaft/Decline Zone t g/t Au oz
A Shaft 710 Complex 1,163,297 4.67 174,812
Deep East 196,967 4.94 31,309
L24 189,780 3.83 23,393
Cartwright 284,082 4.14 37,849
                              Sub-total 1,834,128 4.53 267,363
Hinge Decline Hinge 191,776 3.98 24,564
L13 71,124 3.02 6,915
007 345,201 3.63 40,332
L10 352,372 5.15 58,390
Sub-Total 960,475 4.22 130,201
Cohiba Cohiba 71,902 4.73 10,944
SG-1 and new portal Normandy 1,199,399 4.03 155,557
Total 4,065,904 4.32 564,065
Notes
*Tonnage and grade estimates derived from the Mineral Resource estimate prepared by Lions Gate Geological Consulting (Q.P Susan Lomas, P.Geo), effective date 29 August 2024 (see below). AMC applied a cut-off grade of 2.7 g/t Au to the resource model and then allowed for dilution and mining losses. Gold price used in the cut-off calculation was US$2,500 per ounce, exchange rate of 0.72 CA dollars to one US dollar.

 

Within the “A” shaft, mineralized material will be loaded on the Level 26 loading pocket and skipped to the mill at surface and, for the decline, accessed deposits will be hauled via trucks to the True North processing facility. Processed tailings will be pumped to the central operating and permitted tailings management facility. Development waste is currently planned to be stored on surface and used for ongoing infrastructure projects, including possible tailings dam wall lifts in the future.

 

Processing

 

The fully permitted processing facility operated for a number of years and is reported to have produced 1.93 million oz of gold historically from 9.60 million tonnes at a grade of 6.65 g/t Au. The process plant consists of a crushing and grinding circuit, with a portion of the circulating load passed through gravity concentrators. The concentrate from the gravity concentration is upgraded on a shaking table and the resulting concentrate direct smelted. The tails from the concentration are returned to the head of the grinding mill and the fines from the grinding circuit are fed into a flotation circuit to produce a flotation concentrate which is reground and leached with the remaining process feed using a six-stage carbon-in-pulp circuit. Dissolved gold is then eluted and gold doré is smelted and poured at site with an electric induction furnace.

 

An upgrade of the crushing circuit is required to restart commercial production, otherwise the remainder of the processing plant is intact and recently operated. Historically, the process plant has recorded average recoveries of 94.0% of contained gold and has operated up to 2,250 tpd.

 

Table 6: Mining & Processing Inputs
Mine life – Total years 11
Mining Rate
Underground* tpd 1,215
Total mill feed million tonnes 4.07
Gold grade (diluted) g/t 4.32
Processing
Feed rate* tpd 1,215
Total tonnes processed million tonnes 4.07
Mill head grade g/t Au 4.32
LOM gold recovery % 93.5 %
Notes:
* Steady state average daily mining rate (Years 3 to 8)

 

Tailings Management

 

The Tailings Management Facility is located 1.6 km north of the processing facility in an area naturally defined by bedrock ridges around the perimeter of a flat area. Tailings have been pumped from the processing facility to the TMF via pipeline. During mine operations the tailings are transported as slurry, with 34% solids by weight. An expansion of the facility was completed in 2015 with the construction of the East Tailings Management area, located immediately east of the TMF, including the polishing pond, where water is pumped in and discharged as required. Enough storage exists within the TMF for approximately 775,000 tonnes or over 2 years production under the PEA mine plan and permits are in place to expand the capacity of the TMF as needed.

 

Figure 1. Tonnage Production Profile

 

 Figure 2. Gold Production Profile

 

 Operating Costs

 

Operating costs have been estimated using the following sources and assumptions:

  • Mining unit costs have been estimated based on AMC benchmark data as well as 2025 quotes and 1911 Gold historical costs escalated as per the Bank of Canada inflation calculator.
  • Processing unit costs have been estimated based on AMC benchmark data, as well as 1911 Gold historical costs escalated as per the Bank of Canada inflation calculator.
  • G&A (General and Administrative) costs are based on AMC benchmark data.

 

 

Table 7: Total Life of Mine Operating Costs
Operating Costs (life of mine average)
Mining costs (underground) $/t milled 175
Processing costs $/t milled 38
G&A costs $/t milled 37
Total site operating costs $/t milled 250
Cash Costs
Cash costs (LOM)* US$/oz 1,390
AISC (LOM)** US$/oz 1,897
Notes
*  Cash costs consist of mining costs, processing costs, mine-level general & administrative expenses and refining charges and royalties.
** AISC includes cash costs plus sustaining capital, closure cost and salvage value.

 

Initial and Sustaining Capital Costs

 

The total initial (pre-production) capital cost is estimated to be $59.2 million with an additional $46.7 million of capital during the first 2 years ramp-up period, prior to commercial production. Sustaining capital costs are estimated to be $367.2 million over the LOM (excluding $5.0 million of closure costs and salvage value).

 

The initial and sustaining capital costs were compiled using the following sources:

  • Mining capital costs were developed by AMC, based on the mine plan
  • Processing, infrastructure, project development and project in-directs were developed by AMC, and are inclusive of the underground development required to restart production, upgrade of the crushing circuit for the processing plant, camp expansion and other required infrastructure
  • Sustaining capital costs consist of mining costs including underground resource infill and delineation costs, development costs, tailings storage facility expansions, and water management structures

 

 

Table 8: Total Capital Costs
Description Initial Capital
Cost
Pre-Commercial
Production*
Capital Cost
Total Sustaining
Cost
Total Capital Cost
(millions) (millions) (millions) (millions)
Mining Development $3.3 $29.5 $300.8 $333.5
Process Plant $0.6 $1.5 $6.7 $8.8
Infrastructure On-site $52.8 $6.4 $64.8 $123.9
Total Directs $56.6 $37.4 $372.2 $466.2
Project in-directs including owner’s cost and EPCM $0.5 $1.9 $0.0 $2.4
Contingency $2.0 $7.5 $0.0 $9.5
Total Capital Costs $59.2 $46.7 $372.2 $478.1
Notes:
*Capital during ramp-up in years 1 and 2, prior to commercial production

 

LOM Cash Flow

 

The project is expected to generate $545 million undiscounted after-tax free cash flow (Base Case, see Figure 3.), and $1,314 million undiscounted after-tax free cash flow (at a gold price of US$4,800). Once operational, the mine is expected to support approximately 326 full-time positions, contributing to local employment and regional economic development.

 

Figure 3. LOM Undiscounted After-Tax Free Cash Flow

 

 1911 Gold Opportunities 

 

The PEA results offer consideration of several initiatives that may enhance the Project, including:

 

Processing Capacity & Efficiencies:

  • Existing Processing Capacity – Additional capacity currently exists within the processing plant to increase throughput to the mill with additional mine production.
  • Expand Current Processing Facility – Ability to expand the capacity beyond the current processing capabilities of the plant, by upgrading the secondary crushing circuit and increasing CIP retention time with additional tank capacity

 

Additional Resource Opportunities:

  • Immediate Resource Expansion – Significant potential exists as extensions of the mineral resources used for the PEA mine plan due to the lack of sufficient drilling density.
  • Additional Resource Potential (Mine Footprint) – Recent exploration discoveries within the True North mine footprint occur adjacent to mine infrastructure, with high potential to add resources, including SAM W, SAM SE, and Shore.
  • Potential Addition of New Resources from Regional Targets – Additional resources and resource potential exists within the Rice Lake Greenstone Belt, over a 90-km strike length within 1911 Gold’s 100% owned ~62,000 hectares of ground. The Rice Lake Properties include the Ogama-Rockland gold deposit, all of which have road access, are within trucking distance to the mill, and are proximal to hydro-electric power.

 

Waste Reduction and Operational Efficiencies:

  • Integrated Underground Waste Management – Potential to utilize development waste for rock filling depleted stopes, significantly reducing the volume of waste hoisted to the surface. This strategy is expected to lower operating costs and maximize available shaft capacity for high-grade mill feed.
  • Sensor-based Ore Sorting – Opportunity to implement ore sorting technology to reject waste rock before it reaches the processing facility. This would increase the effective head grade, lower tonnages to be transported and processed, and reduce processing costs per ounce.
  • Advanced Backfill Solutions – Evaluation of tailings paste backfill underground to enhance ground stability and further minimize the surface environmental footprint.
  • Vertical Material Movement Optimization – Transitioning to internal ore passes and gravity-fed systems to move material to the shaft, reducing reliance on diesel-powered haulage and lowering ventilation requirements and related costs.

 

True North Gold Project Mineral Resource Estimate            

 

The Mineral Resource estimate in the PEA was disclosed in the “NI 43-101 Technical Report on the True North Gold Project, Bissett, Manitoba, Canada“, issued on December 24, 2024. The underground 2024 MRE is based on a drill hole database that was rebuilt by 1911 Gold personnel (completed on July 31, 2024) containing a total of 7.960 drill holes, with a total core length of 1,529,232 m.

 

 

Table 9: True North Gold Project: Underground Mineral Resource Estimate
(within 2.25 g/t Au mineral resource constraining envelopes)
Mineral Resource Tonnage Gold Grade Contained Gold
(Category) (t) (g/t) (oz)
Indicated Resources 3,516,000 4.41 499,000
Inferred Resources 5,490,000 3.65 644,000
Notes:
1. The effective date of the MRE is August 29, 2024, which is the date when all scientific and technical data was submitted to Lions Gate Geological Consulting (“LGGC”).
2. The MRE follows the November 29, 2019, CIM Estimation of Mineral Resources and Mineral Reserves Best Practice Guidelines.
3. Mineral Resources are not Mineral Reserves and do not have demonstrated economic viability. There is no certainty that all or any part of the Mineral Resources estimated will be converted into Mineral Reserves. The estimate of Mineral Resources may be materially affected by environmental, permitting, legal, title, taxation, socio-political, marketing, or other relevant issues.
4. The CIM definitions were followed for the classification of Indicated and Inferred Mineral Resources. Indicated Mineral Resources were assigned for blocks with three drill holes within 30 m (100 feet “ft”) and inferred blocks were assigned for blocks with one drill hole within 46 m (150 ft).
5. Ounces and tonnes have been rounded to the nearest 1,000 therefore sums in the table may not add-up due to rounding.
6. Resource constraining envelopes were built around contiguous clusters of blocks at a nominal cut-off grade of 2.25 g/t Au. The mineral resources are reported at a 0.00 g/t Au cut-off within the envelopes. The gold grade threshold for the resource envelopes of 2.25 g/t Au is based on assumptions of a gold price of US$2,000/oz, an exchange rate of US$/C$ 0.75, mining operating costs of C$132/t, processing costs of C$34/t, G&A of C$12/t and average gold recoverability of 94%. The vein solids were built with a minimum width of 1.2 m. This same width was used for the mineral resource envelopes.
7. A bulk density of 2.76 t/m3 (0.086 short tons/ft3) was used to convert volumes to tonnes for all blocks in the mineral resource estimation.
8. The assay gold values were capped to 342.5 g/t Au (10 oz/short ton) and a restricted outlier strategy was applied to each vein to restrict local extreme grades to 15 m (50 ft) from the composite.
9. Gold grades were estimated into a 4.6 m (15 ft) block model using inverse distance squared (ID2) method and 0.46 m (1.5 ft) composited data restricted within the vein solids.

 

1911 Gold Path to Production in 2027

 

The following workflow is anticipated in preparation for True North to commence commercial gold production in 2027:

  • Complete delineation drilling of the areas planned for bulk sampling and mining within the first year of production based on the PEA mine plan
  • Complete infill and resource upgrade drilling of any inferred resources currently planned for production in the first four years of the PEA mine plan, in preparation for inclusion in the planned Pre-Feasibility Study (“PFS“) mine plan
  • Drill test extensions of planned mining areas within the first years of the PEA to add additional resources for inclusion in the PFS
  • Regain access and re-establish infrastructure to all of the underground workings required for the production restart within the first years of production
  • Commence underground development required for the first years of production
  • Assess bulk sample target areas, and complete test mining on targeted zones to test the mining methods, confirm head grades and recoveries and de-risk the project start; and
  • Complete the installation of a new crushing circuit at the mill

 

1911 Gold Planned Exploration (To Advance Alongside Production Readiness):

  • Drill out the new prospective exploration target discoveries located adjacent to mine infrastructure within the True North mine footprint
  • Complete mineral resource estimates on the new discoveries at True North (SAM W, SAM SE, Shore)
  • Complete resource confirmation drilling, preliminary metallurgical test work and provide an updated mineral resource estimate on Ogama-Rockland
  • Complete a PEA study on the new True North and Ogama-Rockland resources to establish the potential economics and plans required to develop these areas
  • Commence a PFS on True North in H2 2026

 

The Company will provide additional details in the NI 43-101 PEA technical report to be filed under the Company’s profile on SEDAR+ and on the Company website within 45 days.

 

Qualified Persons

 

The PEA study was prepared for 1911 Gold as per NI 43-101 requirements by the following Qualified Persons from AMC, and based on the Mineral Resource Estimate completed by LGGC in 2024:

  • Paul Salmenmaki, P.Eng., (AMC)
  • Susan Lomas, P.Geo., (LGGC)
  • Robert Chesher, FAusIMM, (AMC)

 

The scientific and technical information contained in this news release has been reviewed and approved by Michele Della Libera, P.Geo., Vice President of Exploration, and Seok Joon Kim, P.Eng., Chief Engineer of 1911 Gold, who are Qualified Persons within the meaning of NI 43-101. The scientific and technical information pertaining to the PEA has been reviewed and approved by the above mentioned QP’s.

 

About 1911 Gold Corporation

 

1911 Gold is an advanced gold explorer and developer focused on its 100%-owned True North Gold Project in the Archean Rice Lake Greenstone Belt in Manitoba, Canada. The Company controls a large, highly prospective ~62,000-hectare land package with numerous past-producing gold operations within trucking distance of the fully built and permitted True North mine and mill complex. 1911 Gold is positioning itself to restart operations in 2027 and offers a unique, near-term production story with significant exploration upside. The strategy is to build a district-scale gold mining operation around a centralized, and readily expandable infrastructure to support a socially and environmentally responsible, long-term mining operation with little development risk and a growing mineral resource base.

 

1911 Gold’s True North complex and the exploration land package are located within and among the First Nation communities of the Hollow Water First Nation and the Black River First Nation. 1911 Gold looks forward to maintaining open, cooperative, and respectful communications with all of our local communities and stakeholders to foster mutually beneficial working relationships.

 

Posted February 10, 2026

Share this news article

MORE or "UNCATEGORIZED"


Fireweed Metals and Ross River Dena Council Sign Exploration and Collaboration Agreement for Mactung and Macpass Projects

Fireweed Metals Corp. (TSX-V: FWZ) (OTCQX: FWEDF) and the Ross Ri... READ MORE

February 10, 2026

NevGold Intercepts 12.42 g/t AuEq Over 3.1 Meters (3.06% Antimony And 0.53 g/t Au) Within 3.30 g/t AuEq Over 32.0 Meters (0.63% Antimony And 0.87 g/t Au); Significant Oxide Gold-Antimony Mineralization Intercepted in All Step-out Drillholes at Bullet Zone Discovery

NevGold Corp. (TSX-V:NAU) (OTCQX:NAUFF) (Frankfurt:5E50) is pleas... READ MORE

February 10, 2026

GFG Expands Aljo Gold System 150 m East with Step-Out Results of 7.23 g/t Au over 2.0 m as Discovery-Driven Exploration Advances Across Goldarm

GFG Resources Inc. (TSX-V: GFG | OTCQB: GFGSF) reports results fr... READ MORE

February 10, 2026

NGEx Drills 1,246.50m at 0.86% CuEq plus 131.00m at 5.09% CuEq including 5.00m at 29.05% CuEq at Lunahuasi

NGEx Minerals Ltd. (TSX: NGEX) (OTCQX: NGXXF) is pleased to anno... READ MORE

February 10, 2026

Copyright 2026 The Prospector News