Battery Mineral Resources Corp. (TSX-V: BMR) recently completed a seven hole – 687 metre diamond drill program on its 100%-owned Bald Rock target in the Gowganda Project area (Figure 1).
Assay results for the first five holes (189 samples) have been received. Encouraging assay results include:
These intercepts occur in holes drilled into the southern end of the outcrop zone and along strike under sand overburden. The drilling confirmed mineralization extends vertically below and along strike to the south under sand overburden. The extent of the mineralization remains open at depth and along strike to the south of the recently drilled area.
Highlights
About the Bald Rock program
The Bald Rock target is situated in Lawson Township and is also referred to as the LaCarte or Silver Leaf showing. It consists of a shaft that was sunk in the 1930’s and numerous pits and mechanically stripped outcrops which have been periodically examined over the years.
In 2010-2011, a stripped outcrop 250m south of the shaft was grab sampled and yielded an assay of 102,842g/t Ag. In 2011, follow-up exploration consisted of a channel sampling program on the main Bald Rock showing located approximately 500.0m south of the shaft. The channel sampling returned several anomalous mineralized zones including;
Reconnaissance rock grab samples collected by BMR from a prospect pit adjacent to the 2011 channel samples yielded assays of 41.30g/t Ag, 1.53% Co and 7.65% Cu. Stripping and detailed mapping of the outcrop revealed that the altered and mineralized corridor is at least 10.0m wide, extends over a strike length of 40.0m, and is open along strike in both directions.
The vein at the shaft, which was exposed by a pit and stripping, strikes N330oE and yielded an assay of 0.93% cobalt and 5.68g/t silver from a BMR rock grab sample of the vein. The orientation of the vein exposed by the stripping that produced the 102,842g/t Ag assay is located 250m south of the shaft and strikes N350oE, while the main Bald Rock vein system located further south strikes N050oE.
A seven-hole, 687m diamond drill program (Table 1, Figure 2) was completed in late June 2021 to follow up on the significant values obtained from the surface sampling. Five holes tested the depth and strike extent of the Bald Rock vein exposed in the stripped outcrop. The sixth hole targeted the intersection of three mineralised vein sets and a seventh hole targeted an historic high-grade silver rock sample result.
A total of 199 drillcore samples were submitted for assay.
Results from the first five holes (Table 2) indicate that the main outcrop vein zone extends to depth and along strike returning:
Furthermore, the brecciated, fault contact of the Nipissing Diabase with the underlying Huronian sediments yielded:
Battery Minerals Resources CEO, Martin Kostuik, states: “The detailed mapping and sampling at the Bald Rock prospect identified a previously undrilled, 10-metre wide altered and mineralized zone that is open along strike and at depth. BMR’s recent drilling confirmed that the main vein zone of cobalt-silver mineralization extends to depth and along strike. In addition, the anomalous cobalt-silver mineralization identified at the faulted contact of the diabase and sediments indicates that the structure formed contemporaneously with the veining and maybe a conduit for the mineralization, thereby providing an additional target for further exploration.”
Figure 1: Gowganda Project – Bald Rock Location Map
Table 1: Details of the Bald Rock Drill Holes
Drillhole Number |
Easting (m) |
Northing (m) |
Depth (m) |
Dip | Azimuth |
GBR21001 | 529419.50 | 5272483.00 | 132.00 | -45.73o | N313.51oE |
GBR21002 | 529440.50 | 5272529.00 | 78.00 | -46.13o | N316.58oE |
GBR21003 | 529441.70 | 5272556.00 | 60.00 | -44.61o | N315.18oE |
GBR21004 | 529419.60 | 5272483.00 | 123.00 | -60.93o | N312.76oE |
GBR21005 | 529328.70 | 5272520.00 | 162.00 | -44.88o | N132.13oE |
GBR21006 | 529636.20 | 5272689.00 | 81.00 | -45.07o | N311.64oE |
GBR21007 | 529565.60 | 5272803.00 | 51.00 | -45.12o | N075.86oE |
TOTALS: | 7 HOLES TOTALLING: 687.00m |
Figure 2: LiDAR image showing Bald Rock diamond drill hole locations. Inset (in red) highlights the drill holes around the main stripped area. Vein zones (red dashed lines) are projected from measured orientations on stripped outcrop areas
Table 2: Table showing the significant results from holes GBR21001- 005
(Assays for holes GBR21006 and 007 are pending).
Hole ID | From (m) | To (m) | Sample Interval (m) | Cobalt Co (%) | Silver Ag (g/t) | Copper Cu (%) |
GBR21001 | 56.00 | 57.00 | 1.00 | 0.05 | 0.46 | 0.09 |
59.00 | 62.00 | 3.00 | 0.63 | 3.61 | 0.02 | |
including | 59.00 | 59.50 | 0.50 | 0.43 | 0.90 | 0.01 |
59.50 | 60.00 | 0.50 | 0.18 | 0.66 | 0.02 | |
60.00 | 60.75 | 0.75 | 1.62 | 7.64 | 0.01 | |
60.75 | 61.25 | 0.50 | 0.29 | 2.15 | 0.01 | |
61.25 | 62.00 | 0.75 | 0.31 | 4.32 | 0.04 | |
103.50 | 104.50 | 1.00 | 0.04 | 0.58 | 0.30 | |
GBR21002 | 37.70 | 38.50 | 0.80 | 0.05 | 0.81 | 0.07 |
71.30 | 72.00 | 0.70 | 0.05 | 1.56 | 0.11 | |
GBR21003 | 17.00 | 17.80 | 0.80 | 0.06 | 0.52 | 0.02 |
32.10 | 32.70 | 0.60 | 0.05 | 0.48 | 0.03 | |
GBR21004 | 65.75 | 68.25 | 2.50 | 0.28 | 1.01 | 0.05 |
including | 65.75 | 66.75 | 1.00 | 0.64 | 1.32 | 0.01 |
66.75 | 67.75 | 1.00 | 0.01 | 0.05 | 0.01 | |
67.75 | 68.25 | 0.50 | 0.12 | 2.32 | 0.22 | |
81.80 | 82.30 | 0.50 | 0.08 | 1.00 | 0.38 | |
87.90 | 88.40 | 0.50 | 0.19 | 1.03 | 0.12 | |
114.75 | 115.50 | 0.75 | 0.11 | 5.35 | 0.04 | |
GBR21004 | 117.50 | 119.00 | 1.50 | 0.25 | 2.94 | 0.04 |
including | 117.50 | 118.50 | 1.00 | 0.11 | 1.22 | 0.03 |
118.50 | 119.00 | 0.50 | 0.53 | 6.38 | 0.06 | |
GBR21005 | 107.50 | 109.50 | 2.00 | 0.12 | 6.22 | 0.17 |
Note: All Sample Intervals are downhole core lengths
Quality Control
Sample preparation, analysis and security procedures applied on the BMR exploration projects is aligned with industry best practice. BMR has implemented protocols and procedures to insure high quality collection and management of samples resulting in reliable exploration assay data. BMR has implemented formal analytical quality control monitoring for all of its field sampling and drilling programs by inserting blanks and certified reference materials into every sample sequence dispatched.
Sample preparation is performed by ALS Minerals Laboratories (“ALS”) in Sudbury, Ontario and sample analyses by ALS in North Vancouver, British Columbia. ALS analytical facilities are commercial laboratories and are independent from BMR. All BMR samples are collected and packaged by BMR staff and delivered upon receipt at the ALS Laboratory in Sudbury. Samples are logged in a sophisticated laboratory information management system (LIMS) for sample tracking, scheduling, quality control, and electronic reporting. Samples are dried prior to crushing. The samples are crushed to 70% < -2 millimeters and a riffle split of 250 grams is then pulverized to 85% of the material achieving a size of <75 microns. These prepared samples are then shipped to the ALS Laboratory in North Vancouver for analyses by the following methods:
Certified international standards are inserted into sample batches by ALS. Blanks and duplicates are inserted within each analytical run. The blank is inserted at the beginning, internationally certified standards are inserted at random intervals, and duplicates are analysed at the end of the batch.
Additional Information
About Battery Mineral Resources Corp.
Battery is a multi-commodity resource company which provides investors with exposure to the world-wide trend towards electrification. Battery is engaged in the discovery, acquisition, and development of battery metals (cobalt, lithium, graphite, nickel & copper), in North and South America and South Korea with the intention of becoming a premier and sustainable supplier of battery minerals to the electrification marketplace. Battery is the largest mineral claim holder in the historic Gowganda Cobalt-Silver Camp, Canada and continues to pursue a focused program to build on the recently announced, +1 million pound cobalt resource at McAra by testing over 50 high-grade primary cobalt silver-nickel-copper targets. In addition, Battery owns 100% of ESI Energy Services, Inc., a pipeline equipment rental and sales company with operations in Leduc, Alberta and Phoenix, Arizona. Finally, Battery is currently developing the Punitaqui Mining Complex, and pursuing the potential near term resumption of operations at the prior producing Punitaqui copper-gold mine. The Punitaqui copper-gold mine most recently produced approximately 21,000 tonnes of copper concentrate in 2019 and is located in the Coquimbo region of Chile.
Minera Alamos Inc. (TSX-V:MAI) is pleased to announce the executi... READ MORE
Silvercorp Metals Inc. (TSX: SVM) (NYSE American: SVM) and Advent... READ MORE
Vortex Metals Inc. (TSXV: VMS) (FSE: DM8) (OTCQB: VMSSF) is plea... READ MORE
Gatos Silver, Inc. (NYSE:GATO) (TSX: GATO) provided an update on ... READ MORE
Eldorado Gold Corporation (TSX: ELD) (NYSE: EGO) reports the Comp... READ MORE