Endeavour Silver Corp. is pleased to announce the results of a Feasibility Study for its Pitarrilla Project, located in Durango State, Mexico. All amounts are in U.S. dollars unless otherwise stated.
The Study evaluates the development of a mechanized, ramp-access underground mine focused on the Project’s sulphide mineralization and high-grade core. The proposed operation is designed at 4,000 tonnes per day (tpd) of processing capacity and would produce silver-lead and silver-zinc concentrates using conventional crushing, grinding and flotation, with filtered tailings planned for dry-stack facility.
The Study represents an important milestone in advancing Pitarrilla toward a development decision. The Company will file a technical report supporting the Study on SEDAR+ within 45 days of this news release, in accordance with National Instrument 43-101 – Standards of Disclosure for Mineral Projects.
(1) Silver equivalent ratios are calculated using 41 silver oz to 1 lead tonne; 55 silver oz to 1 zinc tonne
Feasibility Study Highlights
“We are excited by the strong Feasibility Study results, which mark a major milestone for Pitarrilla and highlight a compelling opportunity for Endeavour’s next phase of organic growth,” commented Dan Dickson, Chief Executive Officer. “With an anticipated initial 18-year mine life, substantial silver production and an extremely attractive operating cost profile, Pitarrilla has the potential to become a cornerstone asset that delivers lasting value for our shareholders.”
Key Pitarrilla Project Metrics(1)
| Key Assumptions | |
| Silver Price/oz | $50.00 |
| Lead Price/t | $2,028.23 |
| Zinc Price/t | $2,733.70 |
| Foreign Exchange Rate (per $1USD) | MXN 17.00 |
| Project Economics | |
| Life of Mine (LOM) | 18 years |
| LOM Tonnes Processed (t) | 25,078,368 |
| LOM Tonnes Processed per Day | 3,817 |
| Initial LOM Development Meters | 5,437 |
| Sustaining LOM Development Meters | 11,230 |
| LOM Silver Grade (g/t) | 133.41 |
| LOM Lead Grade % | 0.96% |
| LOM Zinc Grade % | 2.27% |
| LOM Silver Equivalent(1)Grade (g/t) | 184.06 |
| LOM Silver Recovery(3)% | 90.90% |
| LOM Lead Recovery(3)% | 96.00% |
| LOM Zinc Recovery(3)% | 91.30% |
| Silver Produced (oz) | 97,780,917 |
| Lead Produced (t) | 231,046 |
| Zinc Produced (t) | 518,900 |
| Silver Equivalent(1)Ounces Produced | 135,523,602 |
| Payable Silver Produced (oz) | 88,669,016 |
| Payable Lead Produced (t) | 214,006 |
| Payable Zinc Produced (t) | 432,853 |
| Operating Cost Metrics | |
| Total Revenue ($ millions) | 6,051 |
| Silver Revenue ($ millions) | 4,433 |
| Silver Revenue as % of Total Revenue | 73% |
| Total Operating Costs (OPEX) ($ millions) | 2,828 |
| Mining Costs ($ millions) | 1,190 |
| Processing Costs ($ millions) | 777 |
| Treatment and Refining Charges (TC/RCs) ($ millions) | 222 |
| Site General & Administrative Costs ($ millions) | 268 |
| Royalty – Third Party Net Smelter Royalty (NSR) – 1.25% ($ millions) | 73 |
| Royalty – Government – 1% Ag, Au Revenue ($ millions) | 44 |
| Special Mining Duty – Government ($ millions) | 254 |
| Total Direct Costs Per Tonne | 109.24 |
| Mining Costs per Tonne | 44.37 |
| Process Cost per Tonne (incl. TC/RCs) | 39.84 |
| G&A Cost Per Tonne | 10.25 |
| Royalties and Special Mining Duty per Tonne | 14.78 |
| Capital Expenditures | |
| Initial Capital Expenditure(2)(CAPEX) ($ millions) | 585 |
| LOM Sustaining Capital Expenditures(2)($ millions) | 119 |
| Total Capital Expenditures(2)(CAPEX) ($ millions) | 704 |
| Total Contingency (Incl. in Total Capital Expenditures) ($ millions) | 68 |
| Project Returns and Unit Costs | |
| EBITDA(2)($ millions) | 2,492 |
| Pre-Tax Payback Period | 4 years |
| After-Tax Operating Cash Flow(2)(Excluding CAPEX) ($ millions) | 2,443 |
| After-Tax Free Cash Flow(2)(including CAPEX) ($ millions) | 1,712 |
| After-Tax NPV (5%) ($ millions) | 736 |
| After-Tax IRR % | 16.37% |
| After-Tax Payback Period | 5 years |
| Capital Efficiency (NPV/Initial Capex) | 1.26 |
| LOM Cash Cost(2), Net of By-Product Credits $/Ag oz | 12.66 |
| LOM AISC(2), Net of By-Product Credits $/Ag oz | 15.06 |
Abbreviations include: NPV = Net Present Value, IRR = Internal Rate of Return, LOM = Life of Mine, AISC = All-In Sustaining Costs
(1) Silver equivalent ratios are calculated using 41 silver oz to 1 lead tonne; 55 silver oz to 1 zinc tonne
(2) These are non-IFRS financial measures. Further details on these non-IFRS financial measures are provided at the end of this press release
(3) Reported metal recoveries refer to recovery to all concentrates combined
Resilient Economics with Silver Price Upside
Pitarrilla demonstrates resilient project economics across the range of silver prices evaluated, with significant leverage to higher silver prices and an estimated break-even silver price below $30 per ounce. At the base-case silver price of $50 per ounce and a 5% discount rate, the Project delivers an after-tax NPV of $736 million and an after-tax IRR of 16.37%. The sensitivity analysis indicates that project value and returns are most responsive to metal prices and comparatively less sensitive to changes in initial capital costs, highlighting Pitarrilla’s strong exposure to silver-price upside.
After-Tax NPV (5%) and IRR Sensitivity to Silver Price
| Silver Price (US$/oz) | $30 | $35 | $40 | $45 | $50 (Base Case) |
$55 | $60 | $65 |
| After-Tax NPV (5%) (millions) | $109 | $266 | $423 | $580 | $736 | $893 | $1,049 | $1,205 |
| After-Tax IRR (%) | 7.00% | 9.62% | 12.03% | 14.26% | 16.37% | 18.39% | 20.32% | 22.16% |
Sensitivity Table – LOM Direct Operating Costs
| Movement | LOM OPEX (millions) |
NPV (millions) |
After-Tax IRR |
| -20% | $2,417 | $906 | 18.85% |
| -10% | $2,623 | $821 | 17.62% |
| Base Case | $2,828 | $736 | 16.37% |
| 10% | $3,034 | $651 | 15.13% |
| 20% | $3,239 | $566 | 13.87% |
Note: Operating Cost sensitivities reflect changes to mining, processing and site indirect costs, while treatment and refining charges, royalties and special mining duty are held at base-case assumptions.
Sensitivity Table – Initial CAPEX
| Movement | CAPEX (millions) |
NPV (millions) |
After-tax IRR |
| -20% | $468 | $840 | 19.85% |
| -10% | $527 | $788 | 17.98% |
| Base Case | $585 | $736 | 16.37% |
| 10% | $644 | $684 | 14.97% |
| 20% | $702 | $632 | 13.73% |
Location and Access
Pitarrilla is located within the Municipalities of El Oro and Inde, on the eastern flank of the Sierra Madre Occidental mountain range in the central part of Durango State, Mexico. The city of Durango, the capital of Durango state, is located 160 kilometres south of the property and the major city of Torreón 160 kilometres to the east.
Pitarrilla is accessible by regional roads. Planned primary access follows approximately 47 kilometres of existing roads, with secondary access via El Palmito. Required upgrades include a permanent bridge over the Nazas River, approximately 11 kilometres from the property.

Property, History, Geology, Mineralization
Pitarrilla is formed by 5 contiguous mineral concessions entitled to Minera Pitarrilla S.A. de C.V. and covering a total area of approximately 4,950 hectares. Minera Pitarrilla is a Mexican corporate entity, and a wholly-owned subsidiary of Endeavour.
The Sierra Madre mountain range preserves remnants of one of Earth’s largest accumulations of intermediate to felsic volcanic rocks, formed in a calc-alkaline magmatic arc during the Eocene to early Miocene, approximately 52–25 million years ago. This volcanism intermittently generated numerous medium- to high-level hydrothermal systems enriched to varying degrees in Ag, Au, Pb and Zn, including epithermal systems in the major Mexican silver districts of the states of Guanajuato, Zacatecas, Durango and Chihuahua. Pitarrilla’s silver-lead-zinc mineralization lies within the Central Mexican Silver Belt, a metallogenic province encompassing these districts.
Endeavour purchased Pitarrilla from SSR Mining Inc. (SSR) for $70 million in 2022, consisting of $35 million in common shares and a further $35 million in cash or in common shares at the election of SSR and agreed to by the Company, and a grant of a 1.25% NSR royalty.
Mine Plan and Production Profile
Pitarrilla is planned as a mechanized, ramp-access underground mine capable of supplying approximately 4,000 tonnes per day to the processing plant. The current design contemplates a mining mix weighted toward transverse and longitudinal long-hole stoping, supplemented by development in ore. The mine plan is expected to target the sulphide mineralization, including Manto Pitarrilla and associated feeder structures. The readily accessible Manto Pitarrilla deposit configuration supports an efficient mine layout with relatively limited underground development required over the LOM. Approximately 16.7 kilometres of total development is planned, comprising 5.4 kilometres during the initial years and 11.3 kilometres of sustaining development thereafter, providing access to the deposit while supporting operating flexibility and efficient, low-cost mining. The current mine plan includes stockpiling over 600,000 tonnes of ore during the construction phase.
Processing and Infrastructure
The proposed 4,000 tpd process plant is expected to include crushing, a grinding circuit incorporating a primary ball mill and a semi-autogenous grinding (SAG) mill, flash, rougher, scavenger and cleaner flotation, concentrate thickening and filtration, and a tailings filtration plant. Filtered tailings are planned to be placed in a dry-stack storage facility. Pitarrilla benefits from year-round road access and an established project footprint with power and water access, exploration infrastructure, contractor facilities and regional access to an experienced workforce.
Capital Investment, Operating Costs and Cash Flow
Initial capital(2) to develop Pitarrilla is estimated at $585 million and is expected to be incurred over a 30-month construction period. Cumulative sustaining capital(2) is estimated at $119 million. Sustaining expenditures are expected to be front-end loaded, as the readily accessible Manto Pitarrilla deposit requires relatively limited development later in the mine life, supporting lower ongoing capital requirements and significant operating flexibility.
LOM average direct production costs(2) are estimated at $109.24 per tonne processed, with cash costs(2), net of by-product credits, of $12.66 per payable oz silver and mine-site AISC(2) (including royalties and special mining duties), net of by-product credits, of $15.06 per payable oz silver.
During full years of commercial production, average annual after-tax free cash flow(1) is estimated at approximately $136 million.
Pitarrilla FS Capital Expenditure Summary
| ($ million) | Initial | Sustaining | Total LOM |
| Mining | $16 | $32 | $48 |
| Mine Equipment | $30 | $74 | $103 |
| Tailings Management Facility | $11 | $9 | $19 |
| Power Supply & Distribution | $77 | – | $77 |
| Mineral Processing Plant | $194 | – | $194 |
| Construction Management | $103 | – | $103 |
| Infrastructure | $90 | $1 | $91 |
| Contingency | $65 | $3 | $68 |
| Total | $585 | $119 | $704 |
Numbers may not add up due to rounding
Pitarrilla FS Operating Cost Summary
| Operating Costs | LOM $ Million | Unit Cost $/processed tonne(2) |
| Mining Costs | $1,190 | $44.37 |
| Process Costs | $777 | $30.97 |
| G&A Costs | $268 | $10.25 |
| Direct Operating Costs | $2,235 | $85.59 |
| Treatment and Refining Charges (TC/RCs) | $222 | $8.87 |
| Royalty – Third Party NSR – 1.25% | $73 | $2.91 |
| Royalty – Government – 1% Ag, Au Revenue | $44 | $1.77 |
| Special Mining Duty | $254 | $10.11 |
| Direct Costs | $2,828 | $109.24 |
Permitting, Environmental and Social Considerations
Pitarrilla has key permits in place for water use and discharge, explosives, change of land use, and underground mining and development under an Environmental Impact Statement. The Company is advancing the additional approvals, amendments and extensions required to reflect the final feasibility design, including the selected tailings-storage facility and related surface infrastructure. Endeavour will continue engagement with local communities, landholders and government authorities as the Project advances.
Opportunities to Unlock Further Value
Advancing Toward a Construction Decision
Endeavour is advancing Pitarrilla toward a construction decision through detailed engineering, procurement planning and project optimization, while progressing the outstanding TSF permit. With its planned long-life production and attractive cost profile, Pitarrilla represents a compelling opportunity to expand Endeavour’s silver production and create lasting shareholder value. Advancing the Project offers a platform for the Company’s next phase of organic growth.
Next steps include:
Mineral Reserves and Mineral Resources
The Study includes updated Mineral Reserve and Mineral Resource estimates incorporating revised mine design, mining methods, dilution and recovery assumptions. Completion of the Pitarrilla Mineral Reserve and Mineral Resource estimates involved the assessment of an updated drill hole database, which included all data for surface and underground drilling completed through October 2025.
Pitarrilla Deposit In-Pit (oxide) and Underground Below-Pit (Transition and Sulphide) Mineral Resource Estimate, Effective Date November 1, 2025
| Cut-Off (AgEq) | Domain/Area | Resource Class | MTonnes | Grade | Contained Metal | ||||||||||
| Ag (g/t) | Pb (%) | Zn (%) | AgEq (g/t) | Ag (Moz) | Pb (Mlbs) | Zn (Mlbs) | AgEq (Moz) | ||||||||
| 50 g/t | Oxide | Indicated | 70.6 | 108 | 0.10 | 0.42 | 120 | 244 | 158 | 659 | 272 | ||||
| Inferred | 9.20 | 82.3 | 0.09 | 0.49 | 96.0 | 24.3 | 18. | .4 | 28.4 | ||||||
| 100 g/t | Transition | Indicated | 18.4 | 141 | 0.48 | 1.11 | 176 | 83.3 | 196 | 449 | 105 | ||||
| Inferred | 2.39 | 172 | 0.50 | 1.46 | 217 | 13. | .2 | 77.0 | 16.7 | ||||||
| 100 g/t | HG Veins | Indicated | 8.49 | 215 | 1.42 | 3.20 | 319 | 58.8 | 266 | 599 | 87.1 | ||||
| Inferred | 3.82 | 194 | 1.28 | 2.52 | 278 | 23.8 | 107 | 212 | 34.2 | ||||||
| Sedimentary Breccia |
Indicated | 16.7 | 118 | 1.02 | 1.62 | 175 | 63.3 | 376 | 598 | 94.2 | |||||
| Inferred | 2.71 | 83.5 | 1.15 | 1.99 | 152 | 7.28 | 68.7 | 119 | 13.3 | ||||||
| Andesite Breccia |
Indicated | 1.97 | 123 | 0.51 | 1.26 | 163 | 7.74 | 21.9 | 54.7 | 10.3 | |||||
| Inferred | – | – | – | – | – | – | – | – | – | ||||||
| Manto | Indicated | 10.6 | 120 | 0.82 | 3.20 | 214 | 40.6 | 191 | 745 | 72.6 | |||||
| Inferred | – | – | – | – | – | – | – | – | – | ||||||
| Sulphide Total | Indicated | 37.7 | 141 | 1.03 | 2.40 | 218 | 170 | 855 | 1,996 | 264 | |||||
| Inferred | 6.53 | 148 | 1.22 | 2.30 | 226 | 31.1 | 176 | 331 | 47.5 | ||||||
| 50 and 100 g/t | Pitarrilla Total | Indicated | 127 | 122 | 0.43 | 1.11 | 157 | 498 | 1,210 | 3,104 | 641 | ||||
| Inferred | 18.1 | 118 | 0.55 | 1.27 | 159 | 68.7 | 221 | 507 | 92.6 | ||||||
Pitarrilla Mineral Reserve Estimate, Effective Date October 30, 2026
| Sulfide Domain | Tonnage (kt) |
Grade | ||
| Ag (g/t) | Pb (%) | Zn (%) | ||
| Probable | ||||
| Andesite Breccia | 2,897 | 150 | 0.79 | 1.82 |
| Manto | 8,726 | 128 | 0.84 | 3.14 |
| Sedimentary Breccia | 13,455 | 134 | 1.07 | 1.79 |
| Total | 25,078 | 133 | 0.96 | 2.27 |
Qualified Persons and Technical Report
The Mineral Resource Estimate was prepared by the following qualified persons. Allan Armitage, Ph.D., P.Geo., of SGS Geological Services. Dr. Armitage completed site visits to the Project on April 14 and 15, 2024, September 23 and 24, 2025 and again on April 12 and 13, 2026. William van Breugel, P. Eng. is an associate engineer of SGS Geological Services, having responsibility for the project economics including capital expenditures, operating expenditures, financials and sensitivities. Johnny Canosa, P. Eng. of SGS Geological Services, having responsibility for the infrastructure, environment, permitting and social or community impact. Henri Gouin, P. Eng. of SGS Geological Services, having responsibility for the mining methods, underground mining planning and schedule. Mr. Gouin conducted a site visit on October 22 and 23, 2024. Shaohai Yu, P. Eng of SGS North America, having responsibility for the mineral processing, metallurgical testing and recovery methods. Mr. Yu conducted a site visit on September 23 and 24, 2025. Diego Cobos, PhD, of SRK Consulting (Colombia), having responsibility for the design of the tailings storage facility and associated water management structures. Mr. Cobos visited the project on 19-22 November 2024 and 16-18 March 2025.
All listed qualified persons are independent Qualified Persons as defined by NI 43-101.
The Company expects to file a technical report supporting the Study on SEDAR+ within 45 days of this news release.
Non-IFRS Financial Measures
The Company has included certain non-IFRS measures in this document as discussed below. The Company believes that these measures, in addition to conventional measures prepared in accordance with IFRS, provide investors an improved ability to evaluate the underlying performance of the Company. The non-IFRS measures are intended to provide additional information and should not be considered in isolation or as a substitute for measures of performance prepared in accordance with IFRS. These measures do not have any standardized meaning prescribed under IFRS, and therefore may not be comparable to other issuers.
Please see the September 30, 2026 MD&A for explanations and discussion of these non-IFRS and other non-financial measures and ratios. Certain additional disclosures for these non-IFRS measures have been incorporated by reference and can be found in the section “Non-IFRS Measures” in the September 30, 2026 MD&A available on SEDAR+ at www.sedarplus.com.
Cash cost (“Cash cost”) per ounce
Cash cost per ounce is a non-IFRS measure. In the silver mining industry, this metric is a common performance measure that does not have a standardized meaning under IFRS. Cash costs include direct costs (including smelting, refining, transportation and selling costs), royalties and special mining duty and changes in finished goods inventory net of by-product credits.
Mine Site – All-in sustaining costs (“MAISC”) and All-in sustaining cost (“AISC”) per ounce
MAISC and AISC per ounce are non- IFRS measures. These measures are intended to assist readers in evaluating the total cost of producing silver from operations. While there is no standardized meaning across the industry for AISC measures, the Company’s definition conforms to the definition of AISC as set out by the World Gold Council and used as a standard of the Silver Institute. The Company defines AISC as the cash operating costs (as defined above), reclamation cost accretion, mine site expensed exploration, corporate general and administration costs and sustaining capital expenditures. For the purpose of this press release, MAISC does not include corporate general and administration costs or mine site expensed exploration.
Free cash flow
In the mining industry, free cash flow is a common performance measure with no standardized meaning. The Company calculates free cash flow by deducting cash capital spending (capital expenditures, net of expenditures paid through finance leases) from net cash provided by operating activities.
The Company discloses free cash flow as it believes the measure provides valuable assistance to investors and analysts in evaluating the Company’s ability to generate cash flow after capital investments and build the cash resources of the Company.
Initial and sustaining capital
Initial and sustaining capital are non-IFRS measures. Initial capital is defined as capital required to develop and construct to bring the mine to commercial production and sustaining capital is defined as the capital required to maintain operations at existing levels. Both measurements are used by management to assess the effectiveness of an investment program.
Earnings before Interest, Taxes, Depreciation, and Amortization (“EBITDA”)
EBITDA represents net earnings before interest, taxes, depreciation and amortization. EBITDA is an indicator of the Company’s ability to generate liquidity by producing operating cash flow to fund working capital needs, service debt obligations, and fund capital expenditures.
Gross revenue and Gross Cost of Sales
Gross revenue represents gross sales of metals and is calculated by adjusting net revenue for the removal of treatment, refining and transportation costs. Gross cost of sales is calculated by adjusting cost of sales for the inclusion of treatment, refining and transportation costs.
About Endeavour Silver
Endeavour is a mid-tier silver producer with three operating mines in Mexico and Peru and a robust pipeline of exploration projects across Mexico, Chile, and the United States. With a proven track record of discovery, development, and responsible mining, Endeavour is driving organic growth and creating lasting value on its path to becoming a leading senior silver producer.
Highlights: Gold equivalent production of 16,985 Gold Equivalent ... READ MORE
Assay-confirmed shallow mineralization; Sulphide-bearing mafic ro... READ MORE
Avalon Advanced Materials Inc. (TSX: AVL) (OTCQB: AVLNF) is ple... READ MORE
Legacy Gold Mines Ltd. (TSX-V: LEGY) is pleased to report assay r... READ MORE