Continental Gold Announces Second Long-Hole Trial Mining Test and Provides Project Update

 

 

 

 

 

 

Continental Gold Inc. (TSX: CNL) (OTCQX: CGOOF) is pleased to provide a project update and announce the commencement of the second long-hole trial mining test at its Buriticá project located in northwestern Antioquia, Colombia.

 

 

Long-Hole Trial Mining Stopes (Figures 1 and 2)

 

 

The second trial mining test will occur in the Yaraguá vein system where ore will be extracted using mechanized long-hole mining from the Hanging Wall vein (“HW2”) (Figure 1). The trial mining test will extract 28.9 metres of total ore from two vertically-stacked stope blocks (see Figure 2). Production estimates for the stopes were calculated using the mineral resource estimate block model in the February 2016 Feasibility Study for the Buriticá Project.

 

 

 

Figure 1: Plan View Showing Location of Proposed Trial Mining Stopes at Yaraguá
 

 

Figure 2: Longitudinal section between elevation of 1,500 and 1,540 metres showing planned upper and lower stope block extraction in HW2 vein
 

 

 

 

The upper stope block will extend 20 metres along strike with a drill height of 13 metres and is anticipated to produce approximately 552 ounces of gold and 1,000 ounces of silver. The lower stope block will extend 20 metres along strike with a drill height of 15.9 metres and is anticipated to produce 310 ounces of gold and 652 ounces of silver. The average stope width for both the upper and lower blocks will be 2.3 metres, calculated by aggregating the HW2 vein width of 1.7 metres and 0.3 metres of over-break material on each stope wall.

 

 

 
Table 1: Combined Production Estimate for Two Trial Mining Stopes

 

 

    Tonnes   Vein Dip   Stope Dimensions (m) (LxWxH)   Gold
(g/t)
  Silver
(g/t)
  Contained Gold Ounces   Contained Silver Ounces
Upper Stope Design   1,734   83°   20 x 2.3 x 13   9.90   17.93   552   1,000
Lower Stope Design   1,915   75°   20 x 2.3 x 15.9   5.03   10.59   310   652
Totals   3,649           7.34*   14.08*   862   1,652
* Weighted average calculation
 

 

 

The objectives of this program include crucial technical and safety training for our workforce. In addition, the program will provide further validation, ahead of planned commercial production in 2020, of the mechanized long-hole mining method and its associated criteria for the Buriticá project. Finally, the lower stope block will be drilled to a longer vertical height of 15.9 metres compared to the 13 metres vertical height for all mineable stopes outlined in the feasibility study. If successful, the Company will begin evaluating the feasibility of increasing the stope heights in the mine plan, which, if adopted, would reduce the amount of development required, potentially lowering pre-production underground mining capital costs and post-production sustaining capital costs.

 

 

Site Update (Figure 3)

 

 

 

Figure 3: Drilling and Blasting the Yaraguá Ramp
 

Underground mine development continues to ramp-up well ahead of schedule, mitigating the potential risk of work not being completed in time for planned production start-up in H1 2020. Major development equipment continues to arrive at site and the mining fleet now includes three jumbos and two 10-tonne LHD loaders. Also, a mechanized bolting machine, for use in larger development headings, is scheduled to arrive in late October 2017. The Company is continuing its comprehensive training and safety programs for its employees as they transition from the existing small-scale conventional mine to mechanized mining related activities. Over the past quarter, significant increases in development efficiencies have been realized with expectations for continued improvements in the months ahead.

 

 

Upgrades to the site access road continue and is on schedule to enable major equipment deliveries to begin in the second half of Q4 2017. Site preparations are progressing as planned, with first concrete pour anticipated in late Q4 2017. A modular building supply contract for the majority of the infrastructure facilities was signed with a well-qualified local fabricator. Work is underway on a 3.2-km low-voltage transmission line to provide additional power for mine development and construction activities.

 

 

As announced on September 18, 2017, the Company increased its drill program for calendar year 2017 from 15,000 to 25,000 metres, with eight drill rigs expected to be in operation by early November. Drill program objectives include increasing and upgrading mineral resources to higher classification categories as well as overall mineral resource growth by drilling step-out holes along strike from the Yaraguá and Veta Sur deposits. Additionally, greenfield geochemical anomalies located near existing and proposed infrastructure will be tested with a series of reconnaissance drill holes.

 

 

“We’re extremely pleased with how rapidly the Buriticá project is ramping up,” commented Donald Gray, Chief Operating Officer. “Both underground development and surface construction are achieving our targets and meeting expectations for production start-up in the first half of 2020. As we move forward with this second long-hole trial mining test, we expect that it will add to the valuable information and experience gained from our previous long-hole trial mining success, which validated our confidence that the long-hole method is well-suited for the near-vertical vein systems we find here at Buriticá.”

 

 

About Continental Gold

 

 

 

Continental Gold Inc. is an advanced-stage exploration and development company with an extensive portfolio of 100%-owned gold projects in Colombia. Formed in April 2007, the Company – led by an international management team with a successful track record of discovering and developing large high-grade gold deposits in Latin America – is focused on advancing its fully-permitted high-grade Buriticá gold project to production with first gold pour on track for early 2020.

 

Posted October 10, 2017

MORE or "UNCATEGORIZED"


Oreninc - "Top Ten November 2017"

November 2017 saw 107 deals close in the Canadian financial marke... READ MORE

December 15, 2017

This Week on The CSE - December 4 - 8

As the week begins we are reminded that December 6 is the 100 ann... READ MORE

December 15, 2017

Millrock Closes Non-Brokered Private Placement

Millrock Resources Inc. (TSX-V: MRO) (OTCQX: MLRKF) reports that ... READ MORE

December 15, 2017

K92 Announces Further High Grade Kora Exploration Drill Results from Kora Northern Extension including First Results from Second Drill Cuddy

K92 Mining Inc. (TSX-V: KNT) is pleased to announce results from ... READ MORE

December 15, 2017

Dynacor Produces 7,253 oz of Gold in November 2017

Dynacor Gold Mines Inc.(TSX:DNG) (OTC:DNGDF) is pleased to ... READ MORE

December 15, 2017

Copyright 2017 The Prospector News - Site design by Spyderbaby Productions

Continental Gold Announces Second Long-Hole Trial Mining Test and Provides Project Update | Prospector News
Uncategorized

Continental Gold Announces Second Long-Hole Trial Mining Test and Provides Project Update

 

 

 

 

 

 

Continental Gold Inc. (TSX: CNL) (OTCQX: CGOOF) is pleased to provide a project update and announce the commencement of the second long-hole trial mining test at its Buriticá project located in northwestern Antioquia, Colombia.

 

 

Long-Hole Trial Mining Stopes (Figures 1 and 2)

 

 

The second trial mining test will occur in the Yaraguá vein system where ore will be extracted using mechanized long-hole mining from the Hanging Wall vein (“HW2”) (Figure 1). The trial mining test will extract 28.9 metres of total ore from two vertically-stacked stope blocks (see Figure 2). Production estimates for the stopes were calculated using the mineral resource estimate block model in the February 2016 Feasibility Study for the Buriticá Project.

 

 

 

Figure 1: Plan View Showing Location of Proposed Trial Mining Stopes at Yaraguá
 

 

Figure 2: Longitudinal section between elevation of 1,500 and 1,540 metres showing planned upper and lower stope block extraction in HW2 vein
 

 

 

 

The upper stope block will extend 20 metres along strike with a drill height of 13 metres and is anticipated to produce approximately 552 ounces of gold and 1,000 ounces of silver. The lower stope block will extend 20 metres along strike with a drill height of 15.9 metres and is anticipated to produce 310 ounces of gold and 652 ounces of silver. The average stope width for both the upper and lower blocks will be 2.3 metres, calculated by aggregating the HW2 vein width of 1.7 metres and 0.3 metres of over-break material on each stope wall.

 

 

 
Table 1: Combined Production Estimate for Two Trial Mining Stopes

 

 

    Tonnes   Vein Dip   Stope Dimensions (m) (LxWxH)   Gold
(g/t)
  Silver
(g/t)
  Contained Gold Ounces   Contained Silver Ounces
Upper Stope Design   1,734   83°   20 x 2.3 x 13   9.90   17.93   552   1,000
Lower Stope Design   1,915   75°   20 x 2.3 x 15.9   5.03   10.59   310   652
Totals   3,649           7.34*   14.08*   862   1,652
* Weighted average calculation
 

 

 

The objectives of this program include crucial technical and safety training for our workforce. In addition, the program will provide further validation, ahead of planned commercial production in 2020, of the mechanized long-hole mining method and its associated criteria for the Buriticá project. Finally, the lower stope block will be drilled to a longer vertical height of 15.9 metres compared to the 13 metres vertical height for all mineable stopes outlined in the feasibility study. If successful, the Company will begin evaluating the feasibility of increasing the stope heights in the mine plan, which, if adopted, would reduce the amount of development required, potentially lowering pre-production underground mining capital costs and post-production sustaining capital costs.

 

 

Site Update (Figure 3)

 

 

 

Figure 3: Drilling and Blasting the Yaraguá Ramp
 

Underground mine development continues to ramp-up well ahead of schedule, mitigating the potential risk of work not being completed in time for planned production start-up in H1 2020. Major development equipment continues to arrive at site and the mining fleet now includes three jumbos and two 10-tonne LHD loaders. Also, a mechanized bolting machine, for use in larger development headings, is scheduled to arrive in late October 2017. The Company is continuing its comprehensive training and safety programs for its employees as they transition from the existing small-scale conventional mine to mechanized mining related activities. Over the past quarter, significant increases in development efficiencies have been realized with expectations for continued improvements in the months ahead.

 

 

Upgrades to the site access road continue and is on schedule to enable major equipment deliveries to begin in the second half of Q4 2017. Site preparations are progressing as planned, with first concrete pour anticipated in late Q4 2017. A modular building supply contract for the majority of the infrastructure facilities was signed with a well-qualified local fabricator. Work is underway on a 3.2-km low-voltage transmission line to provide additional power for mine development and construction activities.

 

 

As announced on September 18, 2017, the Company increased its drill program for calendar year 2017 from 15,000 to 25,000 metres, with eight drill rigs expected to be in operation by early November. Drill program objectives include increasing and upgrading mineral resources to higher classification categories as well as overall mineral resource growth by drilling step-out holes along strike from the Yaraguá and Veta Sur deposits. Additionally, greenfield geochemical anomalies located near existing and proposed infrastructure will be tested with a series of reconnaissance drill holes.

 

 

“We’re extremely pleased with how rapidly the Buriticá project is ramping up,” commented Donald Gray, Chief Operating Officer. “Both underground development and surface construction are achieving our targets and meeting expectations for production start-up in the first half of 2020. As we move forward with this second long-hole trial mining test, we expect that it will add to the valuable information and experience gained from our previous long-hole trial mining success, which validated our confidence that the long-hole method is well-suited for the near-vertical vein systems we find here at Buriticá.”

 

 

About Continental Gold

 

 

 

Continental Gold Inc. is an advanced-stage exploration and development company with an extensive portfolio of 100%-owned gold projects in Colombia. Formed in April 2007, the Company – led by an international management team with a successful track record of discovering and developing large high-grade gold deposits in Latin America – is focused on advancing its fully-permitted high-grade Buriticá gold project to production with first gold pour on track for early 2020.

 

Posted October 10, 2017

MORE or "UNCATEGORIZED"


Oreninc - "Top Ten November 2017"

November 2017 saw 107 deals close in the Canadian financial marke... READ MORE

December 15, 2017

This Week on The CSE - December 4 - 8

As the week begins we are reminded that December 6 is the 100 ann... READ MORE

December 15, 2017

Millrock Closes Non-Brokered Private Placement

Millrock Resources Inc. (TSX-V: MRO) (OTCQX: MLRKF) reports that ... READ MORE

December 15, 2017

K92 Announces Further High Grade Kora Exploration Drill Results from Kora Northern Extension including First Results from Second Drill Cuddy

K92 Mining Inc. (TSX-V: KNT) is pleased to announce results from ... READ MORE

December 15, 2017

Dynacor Produces 7,253 oz of Gold in November 2017

Dynacor Gold Mines Inc.(TSX:DNG) (OTC:DNGDF) is pleased to ... READ MORE

December 15, 2017

Copyright 2017 The Prospector News - Site design by Spyderbaby Productions